I produce monthly ISA server reports for analysis. I'm aware of a problem
that ISA reverses
dates in non US-English system locales and have applied SP2 which I believe
fixes this problem.
My question is in the main summary report it has all the dates listed and
has server participation,
all our dates up to the first 12 days are reversed (US style mm/dd) and has
'no' for participation. All
the remaining dates are dd/mm format for our locale and have 'Yes' for
participation. Except of course
when the day and month are the same like 11/11, this is always yes.
This has always confused me as I read this as this monthly report does not
include the first 12 days
of data. This is same before and after the ISA SP2 patch was applied
(containing MS 331064)
Is this correct ?, and if so why didn't the patch fix this problem.