Re: How I tract our Progress against baseline 1 in MS project by JulieS
JulieS
Thu Jun 08 06:49:43 CDT 2006
Hi nhkazmi,
Manmeet has nicely given you a method to display the Baseline1 data
graphically in a Gantt chart. However, all variance data (Work
Variance, Start and Finish Variance, Duration Variance, etc) will still
calculate from Baseline and Actual data.
An option to get both the graphic and the variance data to calculate off
the new baseline (Baseline1 in your example) is to use the "Interim
plan" option and copy the Baseline1 to Baseline. If you wish to keep
the original baseline for reference, use Tools > Tracking > Save
Baseline and select the Save interim plan option. Copy Baseline into an
unused Baseline field (Baseline 2 for example). Then go back to Tools >
Tracking > Save Baseline, Save interim plan and copy Baseline1 into
Baseline.
I hope this helps. Let us know how you get along.
Julie
"nhkazmi" <nhkazmi@discussions.microsoft.com> wrote in message
news:92B6E465-8EE9-44FB-9E2C-2483F117BC55@microsoft.com...
>I saved a baseline in my project and after a month few critical chages
> incorporated and save a new base line (baseline 1), now I would like
> to track
> actuals progress with latest base line instead of original baseline