I want to create a project for building a house.
In that project scheme, I want to set start and end hours of each
assignment. However I can't find the way to do this. I can set up start and
end dates though, but I also want hours as well.

Any help appreciated.

RE: setting up working hours by JulieS

JulieS
Mon Oct 30 11:37:02 CST 2006

Hi Pierce,

Wow, aren't you James Bond? Or is it Remington Steel? Sorry, couldn't
resist :-)

To show time as well as a date for your tasks, go to Tools > Options, view
tab and select a date format from the drop down list which shows time.

A word of caution: you should not be entering start dates/times nor finish
date/times in Project as you are constraining the tasks. A start date/time
entered in means to project that you cannot start that task any earlier than
the date/time you entered. Project creates a Start No Earlier than
constraint.

Ideally, the task start date/time and finish date/time should be calculated
based upon the project calendar, the resource's calendar, the task duration,
the predecessor and successor relationship, lead, lag, and task calendars.

I hope this helps. Let us know how you get along.

Julie

"Pierce Brosnan" wrote:

> I want to create a project for building a house.
> In that project scheme, I want to set start and end hours of each
> assignment. However I can't find the way to do this. I can set up start and
> end dates though, but I also want hours as well.
>
> Any help appreciated.
>
>
>