Tasks not listed in PWA
I have created a project in Project Professional 2003 then Imported and
Published the project to the Project server. I have allocated myself as the
resource in the tasks and was expecting the list of tasks to appear in my
list of Tasks in Project web access. There are no new tasks assigned to me
what am I missing.
I am a resource in PWA
Please help :-) Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84872
allow highschool students to get educational discounts
allow highschool students to get educational discounts for microsoft products
as the everchanging society is requiring high schoolers to use these products
and it is may be too expensive for students to purchase.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/community/en-us/default.mspx?mid=b8fc137e-db2f-4062-814f-a0b64487c12d&dg=microsoft.public.project Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84869
how does Project calculate summary progress
Also if anyone has any further comments on the "Work schedule progress
question" post below it would be greatly appreciated Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84858
Order of details under Resource in Who does What Report
I am a very new user of Project 2003 and am trying to edit the Who does What
report. I want to sort the detail under each Resource so that each person
can see a list of their tasks in Start Date order. I have tried editing the
report but nothing seems to generate the list under each resource in this
way. If I canâ??t do this via the report editing options, is there a way round
this? I tried exporting the data to Excel but then all the Tasks and
Resource names ended up in the same column so I would still have to do
further editing every time I need a new report when the plan changes.
Would really appreciate some help.
--
Margaret als Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84853
Network Diagram
Can I generate a network diagram and export it to VIsio?
--
Debra H. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84849
Added Calculated Fields to the Roll-Up tasks
How do I add calculated fields to calculate at the roll-up level? I want the
same equation that is used on a parent's children to be performed on the
parent. Is this possible? The formula is extensive and contains nest
if/thens, I don't believe this will be a problem, however I am drawing a
blank as to where the roll-up tasks would be flagged? I know I could use a
flag, however this would become cumbersome. Microsoft has already used some
sort of flag to make the roll-ups become bold, therefore I believe what I am
looking for to be possible.
Please help,
--
Thanks,
KG Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84842
Work schedule progress question
I have a question about how I should display the following data in project.
I will do this in picture form as it is much easier to understand this way.
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
4h 4h
Task1 ------------
5h 5h 5h
Task2 -----------------
4h 4h 4h 4h 4h 4h
Task3 ----------------------------------
2h 2h 2h 2h 2h
Task4 ------------------------------
1h 1h 1h
Task5 -----------------
Cum 4h 13h 22h 31h 35h 41h 47h 53h 57h 60h
hrs
All these task are subtasks to a summary grouping. For example Task 4 is
scheduled from the beginning of week 6 to the end of week 10 and has 5 hrs
scheduled for each week. Thus the hours are scheduled linearly over each of
the tasks but not over all the tasks combined. If I have completed 30 out of
the 60 hrs I want to show a summary progress bar which runs from the
beginning of week 1 to almost to the end of week 4. If I have completed 53
of the 60 hrs I want the bar to run from the beginning of week 1 to the end
of week 8. I have no idea how to do this. Is this % complete, % work
complete, physical % complete, BCWS, BCWP? Please help. Also, this is an
example case. The real data is 10,000 rows of historical data grouped into
many different outline levels. Also, I know project can do lots of things
like change durations, hours, and all that, but I don't want to do that. I
just want to show what I indicated above for all my summary progress bars. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84837
How to ask for updates in MS project
I am managing a project and there is a lot of participants involved in the
project. I do not have Project server and because the sensitivity of the
busines where I am involved I could not post my project on the web.
How can I electronically request to the project participants (resources) for
an update of a task via e-mail. Is there is way to do it with the project
standard program
Thanks
Jorge Perez Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84828
where can I find a manual for Project 2003
Is there a place I can download the manual for P20ject 2003. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84827
BCWS is zero for the summary task after SP1 upgrade
I installed Project 2003 SP1, and not the BCWS for the summary task is zero.
BCWP and Baseline Cost appear to have the correct numbers.
Any suggestions? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84826
Generation Cube
When generation cube an error (-2147221411), any one help me? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84822
How do I change cells with #### in Project?
For some reason some of my duration, start date and finish date cells say
"####" and I cannot change the information in these cells?
Does anyone know why this happens and/or how to fix it?
Thanks,
Jenna Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84820
Tasks that are dependent not changing start dates
My setup is that I have many fairly small projects. The tasks are of short
duration 1-4 hours normally. If task #1 doesn't get started (For example it
was scheduled to start yesterday, I want the next task to be listed as
starting tommorrow not today as was originally scheduled. I won't necessarily
be opening that project or myslef even know that the task got started late,
but I don't want the next person in line thinking they have a task starting
today when the task above them didn't get done. I don't want it to show up in
their tasks. I have current projects set to 1 day.
I have set my dependencies up FS and added a day lag time. It doesn't seem
to recalculate until I enter something into the task above, but I want it to
keep moving the dates if it doesn't get started.
--
Peg Smith Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84819
projected cost
When I go to "report" in the view menu and select the "cost" option, and
subsequently "budget", I see the five columns. I understand where the
"total cost" statistic comes from, but I don't understand the "projected
cost". How is it calculated and where in the program?
Don Quijote de Nicaragua. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84817
Strikethrough a word
Hello there,
When I complete a task, I would like to put a line through it, but keep it
visible. I'm sure that I've seen this before in a project plan.
Basically I would like to strikethrough the font, just like you can do in
Word. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84813
summary progress
In the tracking gantt view, what is the summary progress bar showing. In
other words what is summary progress? Is it % complete, % work complete, or
something else. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84810
Gannt Chart Question
Currently I'm using a split screen to view the resource sheet and a gannt
chart. as I click on each specific resource, the gannt chart displays the
tasks the respective resource is working on. So far so good...
Now, when right clicking in the open area in the gannt chart, and then going
to bar styles > text - the field under the 'right' row is displayed as
resource names.
Is there any way to simply show the name of the resource that I'm clicking
on in the resource sheet above and his respective percentage allocation
instead of *all* resources assigned to the tasks being shown? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84809
Schedule Progress
I am trying to show schedule progress on a summary bar. For example if I
have 60 hours of work to do over a ten week period, and 30 of these hours are
scheduled to be done in the first four weeks, and I have completed 30 hours I
want my summary progress bar to be 40% of the total summary bar rather than
50%. Consequently if 30 hours were scheduled over the first nine weeks and
the remaining 30 hours were scheduled for week ten, I would want to show the
progress bar as 90% of the total summary bar rather than 50. I thought I
could use a summary progress bar which starts at [start] and ends at [%
complete] to do this, but it doesn't look right. Any help would be
aprreciated Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84807
book pubishing process
I tried to post this question a few mins ago but I am not sure whether I have
managed or not. If this is appears to be a copy I am sorry.
I would like to track my resources in the period of several books pubishing.
I am entering the book's name as the task and the works to be done during the
process as ubtasks and assign resources for each subtask. For ex: I have
editors, graphic designers etc.. I would like to enter the total number of
pages for each book as the target work to be done and would like to ask from
each of my resource to enter the number of pages the have edited that day. Is
this possible? Can anyody help me? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84800
leveling Ressoueces (with different units)
Hi...
Yesterday i sent a Question about leveling the resources. But i think, i
could not explain it good. Let me write it a different way..
I have a task (8 hours). The unit of the resource is %25
So i have:
8-9 9-10 10-11 11-12 13-14.....
0,25h 0,25h 0,25h 0,25h 0,25 h
is there aynway to do it so (without making the unit %100)):
8-9 9-10 10-11 11-12 13-14.....
1h 1h 0 0 Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84792
display total resource graph for project
I want to show summary of total resource used on project as abar graph and
also for key tasks rather than scroll through individual graphs for each
resource. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84791
How do I measure actual progress % versus planned progress %
I am trying to report against my project.
I can't find a way of showing the progress which SHOULD have been made
according to the plan.
I want to show, by project phase, % of activity which was planned to have
completed and % of activity which has actually completed.
Can anyone help ? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84787
Track Estimated vs Actual work
Im trying to track my Estimated vs Actual work. when I enter the Actual Work
the Estiamted Work moves with that and therefore the whole schedule moves.
I want to be able to track my original estimates for reporting and learning
purposes so if I enter Actuals I dont want the Estimates to change.
Is there a way to stop the estimates changing or a better way to do this? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84785
Task Creation Guidelines
Looking for a concise, possibly bulleted list of considerations when
including a task in the project schedule. Envisioning guidelines to:
naming/describing the task, duration (e.g. 8/80 rule), establishing
dependencies, assigning resources. I realize there are probably volumes
written on any one of these characteristics, but I was hoping to maybe get
directed to a single, simple source if one exists. The audience is for the
most part, beginner to intermediate level Project users. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84776
Query - What if?
Hello folks,
Is there a function in Microsoft Project to ask the question "What if?"
(i.e. duration of several tasks changes/delays) and the program automatically
responds (somehow)? This would be in lieu of actually making adjustments to
the schedule and seeing what happens to the schedule! I don't think there is
but I thought I would ask. Thanks in advance!
AJ Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84774
Task Creation Guidelines
Looking for a concise, possibly bulleted list of considerations when
including a task in the project schedule. Envisioning guidelines to:
naming/describing the task, duration (e.g. 8/80 rule), establishing
dependencies, assigning resources. I realize there are probably volumes
written on any one of these characteristics, but I was hoping to maybe get
directed to a single, simple source if one exists. The audience is for the
most part, beginner to intermediate level Project users. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84773
How do I change task duration
in the Project 2003 template "Commercial Construction-1"?
I have saved the file to a different name, so I can edit it for my own use.
Most of the tasks are not relevant for my work, but I can use them to base my
own project on.
How do I unlock these fields so I can put in my own dates?
When I try to change the dates or duration they are always grayed out.
--
Thank you Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84772
Deleted a filter, used by a view, and now cannot open the file
Hello,
I recently deleted a "filter" that was used by a "view". Apparantly that
must have been the default view because now when I try to open the file I get
the following error message:
_____________________________
The filter "V - DDI - ALL - NOHLT" cannot be found
You tried to display a view or use an import/export map that references a
filter that is not available.
- If you are trying to use a view, specify a different filter for the view
- If you are exporting with a map, the export will continue without the
application of a filter.
_______________________________
Then, when I click "OK" or even if I just click on the "X" in the upper
right hand corner I get the send error report message. Once that message
comes up the application hangs until I click either the "Send Error Report"
or "Don't Send" buttons.
My problem is that I can't get into the file to fix the filter/view problem.
Any suggestions?????
Thanks in advance for your help :)
Justine Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84766
Multiple Resources & Resource Calendar
I have three resources that must meet to discuss as situation. I assigned all
three resources to the one task.
However, one of the three will be absent on specific date so I updated that
resource's calendar accordingly. When Project 2002 Professional determines
the start/finish dates, it uses the day the one resource is absent. If
remove the available resources, it does not schedule on that day.
Is there a way (other that updating each resource's calendar to say they
aren't available even though two are) to tell Project that all three
resources must be present and thus, not to schedule the day the one resource
is absent?
--
Thank you,
Michael Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84764
Level by priority
Is there any way to make project level by priority first, then by task
duration? "Priority, Standard" does not seem to do it- my short, high
priority tasks are still being delayed by lengthy low-priority ones. I
don't want to use the do not level setting because not all of these
high-priority tasks are of the same importance. Thanks for any help.
Peter Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84758
Resource graphs
I want to display graph showing aggregated resources asigned to project,
rather than separate graphs for each resource. If possible subset showing
resources by task and groups of resources Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84755
Print preview screen is greyed out.
Can only print to the default printer on preview screen can't change to
another printer selection is greyed out. Everything else works fine when
printing File->Print and you can select printers that way, but not from
preview screen. I reinstalled project, haven't installed SR-1 for it yet but
going to.. Does anybody have any other ideas? (using 2000 Project)
Thanks in adavance Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84754
Project Ownership
I know how to edit the ownership of a Project in Web Access and I also know
how to change the ownership in Project Pro. Is there a way that when the
ownership is changed in Project Pro that the ownership in Web Access is
automatically changed so that you don't have to go through those steps in
both places?
--
DMW Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84750
View Specific Date Range
I have a 5-year project schedule. My boss needs a way to view only a
3-month period (July 1, 2005 - September 30, 2005). I know I can print a
specific date range and filter a view for start date ranges.
However, I haven't been able to figure out how to view a range where I have
all tasks which start during the period and may finish after the end date (of
the desired view). I would need for Project to slice the gantt chart on the
desired end date.
Example:
Task A starts on 7/15/2005 and ends 6/1/2006. I want the gantt chart to
only show 7/15/2005 through 9/30/2005 (for now) and keep the rest hidden.
Thanks for any input.
RC Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84744
inserting subprojects
Is there any way when inserting subprojects into the master schedule, that
the number sequence can be consectutive? Or is each subproject inserted
starts from 1? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84733
level ressources with different units
Hello..
there are two parallel tasks. They have the same ressource with diffrent
units.
For example:
task1 Ressource1(%25)
task2 Ressource1(%100).
when i try to level them automatic, one of the tasks will be done after the
other. But i want that they go parallel..
Any idea?
thx... Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84731
How can I have task data adjusted to wrap in Printing?
In Project 2000 it is easy to get data to wrap on screen, but can this then
be printed. It seems to just print as one line and lop off what is too long
for the field width. If the width is adjusted to print as one line, then the
text is too long. I have cut down the task description to the bare minimum
already! Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84730
How to Convert a group of selected tasks in mpp to pdf?
I want to convert a group of selected tasks in .mpp file to pdf file, could
any body please help me?
Thank you in advance Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84729
How to Convert a group of selected tasks in mpp to pdf?
I want to convert a group of selected tasks in .mpp file to pdf file, could
any body please help me?
Thank you in advance Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84726
PWA - Project (Group) Web Sites
We are using MS Project 2003 & Project Server;
Is it possible to have many projects link to a single 'Share Point Services'
web address...??
My reason for this is that we have project managers who manage several
concurrent projects (ie a group of similar projects, for example ~ 'subsea
equipment projects' and 'surface equipment projects'), and our intention is
to have a website for a group of projects.
I cant see how to do this from the Manage Windows SharePoint Services page.
Any advice would be appreciated,
Kevin,
Perth, Western Australia Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84725
Export Summary Tasks to Excel
When I export from MSPrj2K to Excel the Summary activities are not included.
I have checked the Show Summary box in the filter as well as on the
Tools/Options/View tab.
How do I get the related Summary lines to export?
Thanks Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84723
How to resolve a gap in task ID numbering
I have a Project 2003 schedule that's been published to Project Server. In
Project, the task IDs have a gap, like this:
1
2
3
8
9
Tasks 4 through 7 are not shown. The schedule has no filtering, sorting, or
grouping applied. I've tried resorting by ID but with no luck. The missing
tasks 4 through 7 are simply nowhere to be found in Project.
I mentioned that this schedule has been published to Project Server. There,
can see the mystery tasks 4 through 7 in the Project Center view.
Back in Project, I'd like to show the missing tasks 4 through 7, delete
them, and have Project correctly renumber the remaining tasks. Any
suggestions on how to accomplish this?
Thanks, Carlchat Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84720
Percent complete not rolling up to 100% - Project 2003
When I set all the subtasks to 100%, the summary task only show 99%. I can't
change the summary task % to 100 - it goes back to 99%.
I can't get the tasks to show complete and it is messing up my completed
tasks report and driving me nuts.
Everyone else on the project has Project 2003, and no one else is having the
problem. To make it worse, when they try to fix my file for me, it doesn't
work, but their files do. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84716
Import/export resource usage data from Project to/fro Excel? Help
I want to manage Resources by Project by Month with % Allocated in Excel and
then to load the data into Project. I want the spreadsheet to look like the
"Resource Usage" view. I can't find a map to make this work. Any advice? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84712
Custom Indicators
I would like tag certain tasks in my project by entering information in
custom text fields (text1, text2 etc.) and have a custom indicator displayed
in the indicators column that identifies the tasks that I tagged so. How do I
do that? Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84708
% Complete not updating to Web Access
If PM updates the % complete in the project plan, without changing the total
work hours, the percent is not updated in the Tasks view for the resources on
the web. We tried publishing all information, and republishing al
assignments, to no avail.
Under collaboration options we also tried both options for 'Publish and new
changed assignments'
We need to do this because we are just getting started with Project Server
and Web Access, and the PMs wanted to just update the hundreds of already
started and completed tasks on ongoing projects, rather than have all the
resources enter all that actual time.
Any help is appreciated. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84700
Duration changes with multiple resources
I have a project whose tasks total 600 hours. Of the 600 hours there are
tasks and sub-tasks. If I add multiple resources (let's say 3 resources) for
each task, the duration for each task shows 1/3 of the time of the total
task. (i.e. a task estimated at 30 hours will show a duration of 10 hours
after adding 3 resources at 100%). Project will also pull in the finish dates
reflecting 10 hours of work instead of 30 (which is fine).
How can I get Project to continue to reflect the actual total number of
hours of effort (in this case 600) with multiple resources performing each
task? My objective is to show that the project requires 600 hours of effort,
but will not require 600 consecutive hours for completion.
Thanks. Tag: How can I send tasks from project 2002 to my outlook calendar? Tag: 84695