As I input actual start dates the start date also changes. Can I track the
original start date vs actual start date in any report? I would like to
compair the 2 dates in weekly meetings.

Re: save start date to compair with actual start date. by JulieD

JulieD
Sun Jan 09 09:48:31 CST 2005

Hi

prior to entering the actual information, baseline your project (tools /
tracking / save baseline), this will give you the ability to compare actual
to planned. You can also use the tracking gantt view to see both the
baseline & actual (current) on the same gantt chart.

Cheers
JulieD

"lhankg" <lhankg@discussions.microsoft.com> wrote in message
news:4D9A5E01-6354-446E-9EB8-01EAF1F58D0D@microsoft.com...
> As I input actual start dates the start date also changes. Can I track
> the
> original start date vs actual start date in any report? I would like to
> compair the 2 dates in weekly meetings.