Mike
Wed Jul 07 14:53:05 CDT 2004
Hi Gert-Jan ,
Welcome to this Microsoft Project newsgroup :-)
From the Gantt Chart view, select all the tasks (Button above the ID
Column), then click the Assign Resources tool button (the one with two
heads). Type in DoJo. Now select Don Johnson and click the Replace...
button, and repeat for DJ. Finally, go to the Resource Sheet view, select
the two old names and Delete.
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on :-))
Mike Glen
MS Project MVP
"Gert-Jan Schoenmakers" <gj.schoenmakers_XXX@hccnet.nl> wrote in message
news:40ec47d9$0$772$3a628fcd@reader10.nntp.hccnet.nl...
> Hi!
>
> In MSP 2003 I added some resources, for example Don Johnson and DJ. If I
> want to replace these two resources with, for example DoJo and add up
their
> tasks, how can I do this?
>
> Kind regards,
>
> Gert-Jan
>
>