Hi,
I'm sorry to confirm that resource levelin can only postpone taks, so that
as late as possible tasks can never be leveled by Project.
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Tarmo" <Tarmo@discussions.microsoft.com> schreef in bericht
news:FBB96273-265A-45BD-8560-57867553321B@microsoft.com...
> I try manage customer orders. Aim is to push received orders as late as
> possible (but not later than dead-line) because then I can process
incoming
> urgent orders at once. Setting of activities are next: as late as
possible,
> fixed work, limitted resources, fixed minimum lags. But resource levelling
> dont work. What should I do? I need something like automatic activities
> movement in time scale.