JulieS
Fri Jun 27 08:54:26 CDT 2008
Hello shedseven,
No, sorry. To the best of my knowledge, Project does not have the
capacity to draw such a Resource Gantt chart. If a task has multiple
resource assigned it will show the task as you note, with Resource1,
Resource 2.
Have you considered using the left side of the Resource Usage view?
You can add Start and Finish to the Usage table and just print the
left side of the view. No pretty Gantt bars though.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"shedseven" <shedseven@discussions.microsoft.com> wrote in message
news:600FCA9A-5A2E-4AE2-9486-4E147AD4F8E1@microsoft.com...
> Thanks for the quick reply Jan, that is what I did to get the below
> items :)
>
> What I want is for the items that I can currently get to, which is:
>
> Resource 1
> Task 1 xxxxxxxxxxxxxxxxxxxx
> Task 2 xxxxxxxxxxxxxxxxxx xx
> Task 3 xxxxxxxxxxxxxxxx
> Resource 2
> Task 16 xxxxxxxxxxxx
> Task 5 xxx xxxx
> Task 44 xxxxxxxxxxxxxxxx
>
> Resource 1, Resource 2
> Task 8 xxxxxxxxxxxxxxxxxxxx
> Task 9 xxxxxxxxxxxxxxxxxxxx
>
> To be displayed as:
>
> Resource 1
> Task 1 xxxxxxxxxxxxxxxxxxxx
> Task 2 xxxxxxxxxxxxxxxxxx xx
> Task 3 xxxxxxxxxxxxxxxx
> Task 8 xxxxxxxxxxxxxxxxxxxx
> Task 9 xxxxxxxxxxxxxxxxxxxx
> Resource 2
> Task 16 xxxxxxxxxxxx
> Task 5 xxx xxxx
> Task 44 xxxxxxxxxxxxxxxx
> Task 8 xxxxxxxxxxxxxxxxxxxx
> Task 9 xxxxxxxxxxxxxxxxxxxx
>
> This will allow me to hand out lists of tasks to the team members (I
> am 90%
> of the way there, I just need the final bit.
>
> Any ideas or is that confirmed item as good as it gets, because I
> have seen
> the image of the tasks shown in teh form above but I can only get it
> to the
> group level.
>
> Thanks
>
>
>> Hoi,
>>
>> Project Menu
>> Group by...
>> More Groups
>> New
>> Give a group name
>> In Group By select Resource Names
>>
>> OK, OK, Appl;, etc
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>>
http://users.online.be/prom-ade/Calendar.pdf
>> "shedseven" <shedseven@discussions.microsoft.com> wrote in message
>> news:1A6D7BD0-5BF0-4675-B63F-D409A2691D95@microsoft.com...
>> > Hello,
>> >
>> > Did anyone get to the bottom of this? I have seen an image of
>> > this exactly
>> > as you describe but I have been trying to replicate this in
>> > Project to no
>> > avail. The closest I have got is a view of the resources using a
>> > custom
>> > group
>> > and this is by resource name but even this is not perfect
>> > (because I
>> > cannot
>> > see ALL tasks for a resource together because it is like this:
>> >
>> > Resource 1
>> > Task 1 xxxxxxxxxxxxxxxxxxxx
>> > Task 2 xxxxxxxxxxxxxxxxxx xx
>> > Task 3 xxxxxxxxxxxxxxxx
>> > Resource 2
>> > Task 16 xxxxxxxxxxxx
>> > Task 5 xxx xxxx
>> > Task 44 xxxxxxxxxxxxxxxx
>> >
>> > Resource 1, Resource 2
>> > Task 8 xxxxxxxxxxxxxxxxxxxx
>> > Task 9
>> > xxxxxxxxxxxxxxxxxxxx
>> >
>> > Which isn't perfect, like I said I HAVE seen this but I cannot
>> > get the
>> > right
>> > answer just yet.
>> > "Brad" wrote:
>> >
>> >> wasn't sure if someone had figured a solution yet, but posting a
>> >> question
>> >> submitted in July from someone else. I am looking for the same
>> >> solution,
>> >> or
>> >> rather the boss is.
>> >>
>> >> Hi,
>> >>
>> >> In the Resource Usage view, Is there a way of showing the Gantt
>> >> Bars
>> >> for each task that each Resource is working on. I cannot get the
>> >> Gantt
>> >> bars to show up in this type of view. I'll try to demonstrate:
>> >>
>> >> Resource 1
>> >> Task 1 xxxxxxxxxxxxxxxxxxxx
>> >> Task 2 xxxxxxxxxxxxxxxxxx xx
>> >> Task 3 xxxxxxxxxxxxxxxx
>> >> Resource 2
>> >> Task 16 xxxxxxxxxxxx
>> >> Task 5 xxx xxxx
>> >> Task 44 xxxxxxxxxxxxxxxx
>> >>
>> >>
>> >> where 'xxxxx' is the project timeline for each task.
>> >>
>> >> Thanks in advance.
>> >>
>>
>>
>>