Fei
Thu May 08 19:56:00 CDT 2008
thanks Dave
This resopnse helped me to understand the concept better :)
"Dave" wrote:
> It would have helped to have included references to the original
> question to help set the context.
>
> However as I understood the issue at the time, you had a plan and you
> wanted to be able to view who did what work as opposed to who was
> originally planned to do the work.
>
> Firstly, set a baseline (Tools/Tracking/Baseline). This will record the
> resource assignments that exist at the outset.
>
> Then if you go to either the Resource Usage or Task Usage view, you can
> right click on the right hand table and add the baseline work field, the
> work field and the actual work field.
>
> This will allow you to see how the actual work assignments differed from
> the orignial baseline assignments.
>
> I used the term resource-centric to mean that from the Resource Usage
> view you can see on a resource-by-resource basis how the individual's
> assignments have changed from the original plan to now. Similarly, you
> can do the same on a task-by-task basis in the Task Usage view.
>
> Please provide some feedback as to whether or not this answers your
> question.
>
> Fei wrote:
> > thanks Dale,
> > Dave has helped me with a question previously. he said
> > "You could use the baseline work field. Essentially what you are
> > describing is a problem of how to view the actual work carried out by
> > resources on a task against what you originally planned should take
> > place. Because of this you are looking at a resource-centric or
> > task-centric view and you can get this information from either the
> > Resource or Task Usage views.
> > "
> >
> > please see the link
> >
http://www.microsoft.com/office/community/en-us/default.mspx?dg=microsoft.public.project&mid=c6bb95d5-e793-4cf8-8372-8b8dced07e58&sloc=en-us
> >
> > Maybe there isn't a function to set resource/time/task centric in MSP, maybe
> > they are just the ways that a project can be viewed and managed. i.e.
> > methodology?
> >
> >
> >
>