I am trying to display histograms for several resources in the same view
simultaneously. I can do this by exporting resource usage chart into Excel
and using the graphs package. However, I was wondering if anyone knows of a
way of doing this in Project 2003 without having to export the information ?

Thanks, Hutch

Re: In project 2003 can muliple resources be shown in resource graph ? by Jan

Jan
Mon May 21 08:21:04 CDT 2007

Hi,

I'm afraid this is not possible, sorry

--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"Hutch" <Hutch@discussions.microsoft.com> wrote in message
news:A150E9D5-DDB9-4E87-852D-B8BCFA0641AF@microsoft.com...
>I am trying to display histograms for several resources in the same view
> simultaneously. I can do this by exporting resource usage chart into Excel
> and using the graphs package. However, I was wondering if anyone knows of
> a
> way of doing this in Project 2003 without having to export the information
> ?
>
> Thanks, Hutch