I try to change a date and the rest of the chart will not adjust to the new
dates automatically

RE: project 2003 by JimAksel

JimAksel
Sun Aug 12 22:34:00 CDT 2007

F9 to recalculate. Tools/Options/Calculate automatic.

You didn't key in dates manually did you???
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project



"John R McArthur" wrote:

> I try to change a date and the rest of the chart will not adjust to the new
> dates automatically
>