Sun Aug 12 22:34:00 CDT 2007
F9 to recalculate. Tools/Options/Calculate automatic.
You didn't key in dates manually did you???
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"John R McArthur" wrote:
> I try to change a date and the rest of the chart will not adjust to the new
> dates automatically
>