I have set my project start and finish date, but my Gantt chart prints an
additional year and half past the finish date. I tried the date range in the
print window, but that isn't changing it either. Does anyone know how to
control this? Thanks!

Re: How do I print the gantt only up to the project finish date? by Mike

Mike
Mon Oct 31 03:10:34 CST 2005

Hi Melissa,

Welcome to the Microsoft Project newsgroup :-)

Please see FAQ Item: 44. Printing Problems

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:-)

Mike Glen
Project MVP

Melissa wrote:
> I have set my project start and finish date, but my Gantt chart
> prints an additional year and half past the finish date. I tried the
> date range in the print window, but that isn't changing it either.
> Does anyone know how to control this? Thanks!