Steve
Sat Nov 12 12:44:12 CST 2005
Logically how is it possible for tasks to behave as you describe? What you
are saying is that if you have 100 widgets to fidget, it will take the SAME
length of time regardless of whether you put one worker or a hundred on the
job. And further, that fidgeting those widgets will start on a specified
date no matter what, even if something has gone horribly wrong and the
widgets haven't even been delivered to the fidgeters yet. How can that
possibly be accurate? I can appreciate that you have very specific
deadlines that must be met but those are the objectives of the plan, not the
plan itself. The utility of MSP is to serve as a reality check to assist
you in figuring out just how to go about it, independently calculating the
dates in your plan so you can see if it is workable or not. To do that, the
model of the plan in MSP must be free to shift around to predict what you're
going to get if the work is performed the way you've assigned it, whether or
not it meets your objectives. If the calculated plan does NOT meet your
objectives, you must do something concrete to change it, not just turn off
the calculations so you can see a Gantt chart that lies about whether it's
going to work the way you want it to. If the plan Project comes up with has
different dates from those you've determined that you need, you shouldn't
just force it to display the plan the way you want it - it's telling you
that if you try to work the plan the way you've input it into project, it
will fail. To prevent that, you need to change the plan, not Project's
picture of the plan.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"Kevin" <Kevin@discussions.microsoft.com> wrote in message
news:EE27B2F2-8D4A-4A5A-A28A-E8260A5C5372@microsoft.com...
> Hi,
>
> hope someone can help, the nature of my project and the groundwork done
> means that I know all my tasks and start and finish dates, I am working to
> an
> end date that cannot move. I have a lot of tasks that must occur
> simulataneously and no matter what resources are required they will finish
> on
> a certain date.
>
> I have enetered tasks into Project 2003 and the start & finish dates for
> each. The purpose being to make it easier to share and relay milestones +
> highlight reports on activities and progress.
>
> I now need to join them (the tasks) up to give me critical path etc and
> demonstrate dependencies but whenever I do this Project auto finish starts
> the tasks. This then impact the whole project.
>
> They are not all FF, SF, SS or FS, some just overlap and simultaneous
> items.
>
> I don't want to have to lag and lead each line to fit MS Project approach
> to
> handling dependencies, it would take ages. Is there a way to make project
> respect the dates for start and finish that I have enetered and not be too
> clever, auto lagging or lead where necc but at all times preserve the
> dates
> that I have enetered.
>
> Many thanks,