JulieS
Wed May 23 17:37:39 CDT 2007
Hi Confused,
Thanks so much for the kind words -- I'm glad to help. There isn't any
pay involved with any of the volunteers who answer questions here , but
I can say without fear of contradiction, when folks like you post such
nice comments -- that's the only "pay" we ever need :-)
To your question, changing max. units in a file (resource pool or
otherwise) *may* cause problems if you *drop* the max. units. Changing
the max. units for a resource *after* assigning the resource does not
change assignment units to tasks. So, if you drop the max. units below
100% but have resource assigned at 100%, you will create overallocations
because a resource is assigned at above his/her max. units.
If you want to change max. units and have the resource assigned at the
new max units, use the Assign resources dialog box to remove the
resource and replace with the same resource using the lower assignment
unit. Select all tasks in the project and click the Assign Resources
button. Select the resource you want to re-assign in the list. Click
the replace button and in the replace dialog box, select the same
resource -- enter in the lower assignment units.
Do be prepared however that droppping resource assignment units will
usually extend the duration of your tasks. You will see dates shift :-)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"Confused" <Confused@discussions.microsoft.com> wrote in message
news:B492515D-513E-4C4C-BD82-57888637FE74@microsoft.com...
> You are so patient and willing to help. I hope you get paid for this!
>
> Does changing the max units for a resource in a pool cause any
> problems?
> --
> Thanks.
> Confused
>
>
> "JulieS" wrote:
>
>> Hi Confused,
>>
>> Sorry for the delay in responding. I'm glad to know things are a bit
>> clearer about the overtime work/cost questions and thanks for the
>> feedback.
>>
>> To your new question about Max. Units. I'm sure you'll get other
>> opinions on this one but as you asked, here's my thoughts and
>> comments.
>>
>> You note the instructor told you not to fill in max. units. I assume
>> the instructor meant to leave the unit to the default of 100% and not
>> to
>> drop the max. units fields below 100% to reflect that a resource
>> cannot
>> devote "full time" to a project.
>>
>> If a resource truly only works part time (they work 4 hours per day
>> on
>> Monday through Friday) I would most definitely change that resource's
>> calendar with the specific 4 hours per day they work and *possibly*
>> leave the max. units at 100%. By changing the resource's calendar, I
>> am
>> restricting the times the resource can work on tasks. If a task is
>> scheduled to start at 3:00 pm and Bob is the sole resource assigned
>> but
>> he only works from 8:00 am to 12:00 pm, the task start will change to
>> 8:00 am the next day reflecting Bob's working calendar.
>>
>> On the other hand, I *do* use max. units of less than 100% quite
>> frequently to reflect that a resource cannot gernerate one hour of
>> effort on project tasks for each one hour of working time in the
>> resource's calendar. The max. units field is the default assignment
>> value used by Project when resources are assigned. By setting the
>> max.
>> at less than 100% and entering the work estimate a resource has given
>> me, Project will divide the work estimate by the max units and
>> calculate
>> a duration for the task. So, for example, if the resource Sue works
>> 40
>> per week, but my project sponsor says I can only have half of Sue's
>> time
>> (approximately 20 hours per week). I would set Sue's max. units at
>> 50%.
>> Then in reviewing a work package with Sue, she tells me task G is 20
>> hours of work. If I assign Sue to a 20 hour work task, Project will
>> calculate a task duration of 1 week (40 hours).
>>
>> As I said, you will most likely get other opinions as well :-)
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit
http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "Confused" <Confused@discussions.microsoft.com> wrote in message
>> news:CE7E43DF-D271-41E3-B751-B6BE4FC74C01@microsoft.com...
>> > JulieS:
>> >
>> > Thanks for responding. It took me awhile to get back into this. I
>> > get how
>> > this works and I appreciate your help. Can I add one question? Do
>> > you ever
>> > change the max units field on the resource sheet? I took a class
>> > and
>> > the
>> > instructor warned us to let project calculate that field and use a
>> > resource
>> > calendar to reflect a part time employee (rather than addding 50%
>> > into
>> > that
>> > field). Do you agree with that comment, and if so why? Thanks so
>> > much for
>> > your help. I hope I can figure this application out!--
>> > Thanks.
>> > Confused
>> >
>> >
>> > "JulieS" wrote:
>> >
>> >> Hello Confused,
>> >>
>> >> Project will only calculate overtime costs in situations where you
>> >> have
>> >> put an overtime rate in for the resource(s) assigned to overtime
>> >> work.
>> >> If you wish the overtime work to be "free" you may leave the
>> >> overtime
>> >> rate field blank (set to $0.00 by default). However, leaving
>> >> overtime
>> >> rate set to zero and assigning significant amounts of overtime is
>> >> going
>> >> to skew the relationship between total work and total cost. I
>> >> usually
>> >> suggest setting the overtime rate equal to the straight time rate
>> >> for
>> >> salaried employees. Yes, you don't pay them more for working 50
>> >> hours
>> >> per week, but many companies do accrue costs for "extra" hours
>> >> through
>> >> compensatory time.
>> >>
>> >> As far as Project not shifting the schedule -- I'm afraid that is
>> >> what
>> >> overtime does -- it drops the duration of tasks because the
>> >> overtime
>> >> work assigned during nonworking time as defined in the calendar.
>> >>
>> >> I'm not sure I understand what you are trying to accomplish by
>> >> assigning
>> >> overtime but not having the schedule change. Perhaps a few more
>> >> details
>> >> would help us help you.
>> >>
>> >> I hope this helps. Let us know how you get along.
>> >>
>> >> Julie
>> >> Project MVP
>> >>
>> >> Visit
http://project.mvps.org/ for the FAQs and additional
>> >> information
>> >> about Microsoft Project
>> >>
>> >> "Confused" <Confused@discussions.microsoft.com> wrote in message
>> >> news:0763CC2A-0D6D-4998-8487-415C8D5DEA22@microsoft.com...
>> >> >I am using Project Standard 2003. I have salaried employees that
>> >> >work
>> >> > overtime on tasks, and I do not want Project to calculate a cost
>> >> > associated
>> >> > with those hours, nor do I want Project to shift the schedule
>> >> > when
>> >> > I
>> >> > add
>> >> > overtime hours. Is this possible?
>> >> > --
>> >> > Thanks.
>> >> > Confused
>> >>
>> >>
>> >>
>>
>>
>>