robwright
Sun Jul 02 19:34:02 CDT 2006
Thank you Steve. I can finish my assignment.
Rob Wright
"Steve House" wrote:
> The standard rate usually includes the base cost plus overburden. So in
> your example set the resource's standard rate to $65/hr. IMHO the OT rate
> should be the same $65/hr because even though he doesn't get an overtime
> paycheck usually, just because he's working after 5pm doesn't mean he's
> working for free.
>
>
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit
http://www.mvps.org/project/faqs.htm for the FAQs
>
>
>
> "rob wright" <robwright@discussions.microsoft.com> wrote in message
> news:D3D81103-5CF5-4C56-9FDB-45EE9490588F@microsoft.com...
> > Julie, thanks for getting back so soon. My instructor asked the students
> > to
> > add resources to the project and assign the resources to the sub-task on
> > the
> > project.
> >
> > a. Anaslyst $50.00/hour + 15/hour overburden.
> >
> > Do I charge a total of $65.00 per hour, or is there some other place I
> > should charge the $15/hour overburden rates.
> >
> > thanks Rob Wright
> >
> > "JulieS" wrote:
> >
> >> Hi Rob,
> >>
> >> The cost for the project is calculated by the standard rate for the
> >> resource * the number of hours of work. No burden or overtime is
> >> automatically calculated by Project.
> >>
> >> To see standard and overtime rates, look at the Resource Sheet View.
> >>
> >> --
> >> I hope this helps. Let us know how you get along.
> >>
> >> Julie
> >>
> >> Visit
http://project.mvps.org/ for FAQs and more information about
> >> Microsoft Project.
> >>
> >> "rob wright" <rob wright@discussions.microsoft.com> wrote in message
> >> news:6C0A9780-9D4F-44A9-B2B7-F912131C1EB9@microsoft.com...
> >> > is the overburden rate of 10.00 added to the normal hourly rate in
> >> > microsoft
> >> > project
> >>
> >>
> >>
>
>