Hello all - thanks for any help on a probably obvious question. I am making
all of my tasks 'fixed work' to reflect the fact that our organization is
assigning specific amounts of hours to each resource for a given task. This
was working fine, but I now find that many of my summary tasks have total
hours that are much, much higher than the total of the hours assigned to
subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
for resource B have a total summary task of 226.88 hours!
I assume that Project is somehow extrapolating from task timelines (which I
also sometimes assign, i.e. I manually put in start and finish dates) and/or
resource availability, but how to I stop it from doing this?
Thanks,
Jeff

RE: newby question - project hours dramatically increasing on their ow by JimAksel

JimAksel
Tue Nov 20 12:09:05 PST 2007

A few things. First, make sure you are not assigning resources to summary
tasks. Second, hand key a date only as a last resort since it creates
constraints. Instead, finese durations to get things where you need them.

Fixed work tasks. Key in a value in the [Work] column (work is not the same
as duration). That value should not change regardless of duration. What
will change is the %Units (the allocation of resources assigned to the task).

See if any of that helps.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project



"Jeff" wrote:

> Hello all - thanks for any help on a probably obvious question. I am making
> all of my tasks 'fixed work' to reflect the fact that our organization is
> assigning specific amounts of hours to each resource for a given task. This
> was working fine, but I now find that many of my summary tasks have total
> hours that are much, much higher than the total of the hours assigned to
> subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> for resource B have a total summary task of 226.88 hours!
> I assume that Project is somehow extrapolating from task timelines (which I
> also sometimes assign, i.e. I manually put in start and finish dates) and/or
> resource availability, but how to I stop it from doing this?
> Thanks,
> Jeff

Re: newby question - project hours dramatically increasing on their by Dave

Dave
Thu Nov 22 02:08:41 PST 2007

Jeff wrote:
> Hello all - thanks for any help on a probably obvious question. I am making
> all of my tasks 'fixed work' to reflect the fact that our organization is
> assigning specific amounts of hours to each resource for a given task. This
> was working fine, but I now find that many of my summary tasks have total
> hours that are much, much higher than the total of the hours assigned to
> subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> for resource B have a total summary task of 226.88 hours!
> I assume that Project is somehow extrapolating from task timelines (which I
> also sometimes assign, i.e. I manually put in start and finish dates) and/or
> resource availability, but how to I stop it from doing this?
> Thanks,
> Jeff


Are you absolutely sure that the task type has been configured as 'fixed
work' and is not set to 'fixed units' which is commonly the default?

You can check this by splitting the window from the Gantt view and
checking each task in turn. If the task type were 'fixed units' then
extending the timelines would indeed increase the work and might lead
you think the application was somehow extrapolating.

Also are you sure there are no other tasks under the summary which might
be contributing to the total?

One last thing to check is that you haven't made any typos with the
hours but I am sure you have already checked that. Also check for
consistency with units and that you are always entering explicitly hours
and not days/weeks etc.

RE: newby question - project hours dramatically increasing on thei by Jeff

Jeff
Mon Nov 26 11:19:02 PST 2007

Thanks very much, appreciate your time.
one thing that is a little unclear to me is how to finesse durations. right
now i have many tasks that are not where I want them to be in the overall
timeline - how can I move them to the weeks I want without limiting MSP's
ability to level, etc.?

jeff
"Jim Aksel" wrote:

> A few things. First, make sure you are not assigning resources to summary
> tasks. Second, hand key a date only as a last resort since it creates
> constraints. Instead, finese durations to get things where you need them.
>
> Fixed work tasks. Key in a value in the [Work] column (work is not the same
> as duration). That value should not change regardless of duration. What
> will change is the %Units (the allocation of resources assigned to the task).
>
> See if any of that helps.
> --
> If this post was helpful, please consider rating it.
>
> Jim
>
> Visit http://project.mvps.org/ for FAQs and more information
> about Microsoft Project
>
>
>
> "Jeff" wrote:
>
> > Hello all - thanks for any help on a probably obvious question. I am making
> > all of my tasks 'fixed work' to reflect the fact that our organization is
> > assigning specific amounts of hours to each resource for a given task. This
> > was working fine, but I now find that many of my summary tasks have total
> > hours that are much, much higher than the total of the hours assigned to
> > subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> > for resource B have a total summary task of 226.88 hours!
> > I assume that Project is somehow extrapolating from task timelines (which I
> > also sometimes assign, i.e. I manually put in start and finish dates) and/or
> > resource availability, but how to I stop it from doing this?
> > Thanks,
> > Jeff

Re: newby question - project hours dramatically increasing on thei by Jeff

Jeff
Mon Nov 26 11:20:01 PST 2007

Thanks very much, really appreciate your time.

Jeff

"Dave" wrote:

> Jeff wrote:
> > Hello all - thanks for any help on a probably obvious question. I am making
> > all of my tasks 'fixed work' to reflect the fact that our organization is
> > assigning specific amounts of hours to each resource for a given task. This
> > was working fine, but I now find that many of my summary tasks have total
> > hours that are much, much higher than the total of the hours assigned to
> > subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> > for resource B have a total summary task of 226.88 hours!
> > I assume that Project is somehow extrapolating from task timelines (which I
> > also sometimes assign, i.e. I manually put in start and finish dates) and/or
> > resource availability, but how to I stop it from doing this?
> > Thanks,
> > Jeff
>
>
> Are you absolutely sure that the task type has been configured as 'fixed
> work' and is not set to 'fixed units' which is commonly the default?
>
> You can check this by splitting the window from the Gantt view and
> checking each task in turn. If the task type were 'fixed units' then
> extending the timelines would indeed increase the work and might lead
> you think the application was somehow extrapolating.
>
> Also are you sure there are no other tasks under the summary which might
> be contributing to the total?
>
> One last thing to check is that you haven't made any typos with the
> hours but I am sure you have already checked that. Also check for
> consistency with units and that you are always entering explicitly hours
> and not days/weeks etc.


Re: newby question - project hours dramatically increasing on thei by davegb

davegb
Wed Dec 05 06:42:23 PST 2007

On Nov 26, 12:19 pm, Jeff <J...@discussions.microsoft.com> wrote:
> Thanks very much, appreciate your time.
> one thing that is a little unclear to me is how to finesse durations. right
> now i have many tasks that are not where I want them to be in the overall
> timeline - how can I move them to the weeks I want without limiting MSP's
> ability to level, etc.?
>
> jeff

That's the whole point. Project doesn't schedule tasks to suit our
preconceived notions of when they need to happen. If properly used, it
schedules them to be done at the earliest possible date to take
maxmimum advantage of any availble slack. Of course, you can
reschedule them to later dates to put tasks where you want them in
time, but why? If there is a complelling reason they can't occur until
some date later than their dependencies would dictate, that's what
Constraints are for. But most of us here advise against doing so
arbitralily. It just decreases your odds of completing your project on
schedule and within budget.

Hope this helps in your world.
>
>
>
> "Jim Aksel" wrote:
> > A few things. First, make sure you are not assigning resources to summary
> > tasks. Second, hand key a date only as a last resort since it creates
> > constraints. Instead, finese durations to get things where you need them.
>
> > Fixed work tasks. Key in a value in the [Work] column (work is not the same
> > as duration). That value should not change regardless of duration. What
> > will change is the %Units (the allocation of resources assigned to the task).
>
> > See if any of that helps.
> > --
> > If this post was helpful, please consider rating it.
>
> > Jim
>
> > Visithttp://project.mvps.org/for FAQs and more information
> > about Microsoft Project
>
> > "Jeff" wrote:
>
> > > Hello all - thanks for any help on a probably obvious question. I am making
> > > all of my tasks 'fixed work' to reflect the fact that our organization is
> > > assigning specific amounts of hours to each resource for a given task. This
> > > was working fine, but I now find that many of my summary tasks have total
> > > hours that are much, much higher than the total of the hours assigned to
> > > subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> > > for resource B have a total summary task of 226.88 hours!
> > > I assume that Project is somehow extrapolating from task timelines (which I
> > > also sometimes assign, i.e. I manually put in start and finish dates) and/or
> > > resource availability, but how to I stop it from doing this?
> > > Thanks,
> > > Jeff- Hide quoted text -
>
> - Show quoted text -


Re: newby question - project hours dramatically increasing on thei by Jeff

Jeff
Thu Dec 20 10:01:03 CST 2007

Hi Dave,

Thanks, a few people have pointed out that this is Project's big strength.
It doesn't seem that adapted for my project, which is a consulting project
with a series of deadlines driven by the client, that are not up for
negotiation. All I want to do is produce a Gantt chart with many task dates
fixed by me, and see where this creates large resource demands so I can bring
in more people/plan to camp at the office. The problem I keep running into
is that Project will reassign dates of other tasks when I try to fix a task
timeline with constraints, or it will simply refuse my constraints.
Project's ability to schedule is actually getting in my way at this point,
unless there is some other way to get around it. Meanwhile, my client has
asked that we produce all project plans in Project, so I am stuck with it for
now.

Thanks again,

Jeff

"davegb" wrote:

> On Nov 26, 12:19 pm, Jeff <J...@discussions.microsoft.com> wrote:
> > Thanks very much, appreciate your time.
> > one thing that is a little unclear to me is how to finesse durations. right
> > now i have many tasks that are not where I want them to be in the overall
> > timeline - how can I move them to the weeks I want without limiting MSP's
> > ability to level, etc.?
> >
> > jeff
>
> That's the whole point. Project doesn't schedule tasks to suit our
> preconceived notions of when they need to happen. If properly used, it
> schedules them to be done at the earliest possible date to take
> maxmimum advantage of any availble slack. Of course, you can
> reschedule them to later dates to put tasks where you want them in
> time, but why? If there is a complelling reason they can't occur until
> some date later than their dependencies would dictate, that's what
> Constraints are for. But most of us here advise against doing so
> arbitralily. It just decreases your odds of completing your project on
> schedule and within budget.
>
> Hope this helps in your world.
> >
> >
> >
> > "Jim Aksel" wrote:
> > > A few things. First, make sure you are not assigning resources to summary
> > > tasks. Second, hand key a date only as a last resort since it creates
> > > constraints. Instead, finese durations to get things where you need them.
> >
> > > Fixed work tasks. Key in a value in the [Work] column (work is not the same
> > > as duration). That value should not change regardless of duration. What
> > > will change is the %Units (the allocation of resources assigned to the task).
> >
> > > See if any of that helps.
> > > --
> > > If this post was helpful, please consider rating it.
> >
> > > Jim
> >
> > > Visithttp://project.mvps.org/for FAQs and more information
> > > about Microsoft Project
> >
> > > "Jeff" wrote:
> >
> > > > Hello all - thanks for any help on a probably obvious question. I am making
> > > > all of my tasks 'fixed work' to reflect the fact that our organization is
> > > > assigning specific amounts of hours to each resource for a given task. This
> > > > was working fine, but I now find that many of my summary tasks have total
> > > > hours that are much, much higher than the total of the hours assigned to
> > > > subtasks - for example, 3 subtasks worth 22 hours for resource A and 10 hours
> > > > for resource B have a total summary task of 226.88 hours!
> > > > I assume that Project is somehow extrapolating from task timelines (which I
> > > > also sometimes assign, i.e. I manually put in start and finish dates) and/or
> > > > resource availability, but how to I stop it from doing this?
> > > > Thanks,
> > > > Jeff- Hide quoted text -
> >
> > - Show quoted text -
>


Re: newby question - project hours dramatically increasing on thei by Steve

Steve
Sat Dec 22 01:38:02 CST 2007

Of course you have 'must-hit' deadlines that aren't negotiable - almost all
projects do. But the purpose of software like MS Project is not to document
those deadlines - it's purpose is to provide you with a calculating tool
that will predict outcomes - a what-if modeling tool designed to help you
figure out just how you must organize the workflow and resource assignments
in order to meet those requirements. And for it to do that, it must be
allowed to freely predict the results that you will obtain for any given
trial structure. If Project is insisting on changing task dates where you
don't want it to, it's telling you something very valuable - it's telling
you that it will be impossible for you to meet your required dates with the
workflow and resource assignments as you have entered them. The solution is
not to override Project's scheduling engine with constraints - the solution
is to change your workflow and/or resources until Project's calculated
schedule aligns to the schedule deadlines your client mandates that you
achieve. You cannot fix a task to a certain date by simply declaring that
that is when it will happen - you have to drive it there by some real-world
physical process that insures the preliminary foundation work is completed
in-time for the task in question to begin and the resources with the
required skills are available and in the right place at the right time to do
the work so that the task will be able proceed as you need it to. If
Project's date calculations don't put the tasks where you want them, it
means you haven't discovered the workflow and resource assignments that will
allow them to happen as needed.

In short, you don't tell Project the schedule you want, its job is to tell
you the schedule you'll be able to get with a given workflow organization
and resource loading. If that schedule doesn't meet your business
requirements, you need to experiment with different workflows and resource
assignments until it does.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Jeff" <Jeff@discussions.microsoft.com> wrote in message
news:5EBF2CA6-4859-471C-B2DE-D26C4AE0C94B@microsoft.com...
> Hi Dave,
>
> Thanks, a few people have pointed out that this is Project's big strength.
> It doesn't seem that adapted for my project, which is a consulting project
> with a series of deadlines driven by the client, that are not up for
> negotiation. All I want to do is produce a Gantt chart with many task
> dates
> fixed by me, and see where this creates large resource demands so I can
> bring
> in more people/plan to camp at the office. The problem I keep running
> into
> is that Project will reassign dates of other tasks when I try to fix a
> task
> timeline with constraints, or it will simply refuse my constraints.
> Project's ability to schedule is actually getting in my way at this point,
> unless there is some other way to get around it. Meanwhile, my client has
> asked that we produce all project plans in Project, so I am stuck with it
> for
> now.
>
> Thanks again,
>
> Jeff
>
> "davegb" wrote:
>
>> On Nov 26, 12:19 pm, Jeff <J...@discussions.microsoft.com> wrote:
>> > Thanks very much, appreciate your time.
>> > one thing that is a little unclear to me is how to finesse durations.
>> > right
>> > now i have many tasks that are not where I want them to be in the
>> > overall
>> > timeline - how can I move them to the weeks I want without limiting
>> > MSP's
>> > ability to level, etc.?
>> >
>> > jeff
>>
>> That's the whole point. Project doesn't schedule tasks to suit our
>> preconceived notions of when they need to happen. If properly used, it
>> schedules them to be done at the earliest possible date to take
>> maxmimum advantage of any availble slack. Of course, you can
>> reschedule them to later dates to put tasks where you want them in
>> time, but why? If there is a complelling reason they can't occur until
>> some date later than their dependencies would dictate, that's what
>> Constraints are for. But most of us here advise against doing so
>> arbitralily. It just decreases your odds of completing your project on
>> schedule and within budget.
>>
>> Hope this helps in your world.
>> >
>> >
>> >
>> > "Jim Aksel" wrote:
>> > > A few things. First, make sure you are not assigning resources to
>> > > summary
>> > > tasks. Second, hand key a date only as a last resort since it
>> > > creates
>> > > constraints. Instead, finese durations to get things where you need
>> > > them.
>> >
>> > > Fixed work tasks. Key in a value in the [Work] column (work is not
>> > > the same
>> > > as duration). That value should not change regardless of duration.
>> > > What
>> > > will change is the %Units (the allocation of resources assigned to
>> > > the task).
>> >
>> > > See if any of that helps.
>> > > --
>> > > If this post was helpful, please consider rating it.
>> >
>> > > Jim
>> >
>> > > Visithttp://project.mvps.org/for FAQs and more information
>> > > about Microsoft Project
>> >
>> > > "Jeff" wrote:
>> >
>> > > > Hello all - thanks for any help on a probably obvious question. I
>> > > > am making
>> > > > all of my tasks 'fixed work' to reflect the fact that our
>> > > > organization is
>> > > > assigning specific amounts of hours to each resource for a given
>> > > > task. This
>> > > > was working fine, but I now find that many of my summary tasks have
>> > > > total
>> > > > hours that are much, much higher than the total of the hours
>> > > > assigned to
>> > > > subtasks - for example, 3 subtasks worth 22 hours for resource A
>> > > > and 10 hours
>> > > > for resource B have a total summary task of 226.88 hours!
>> > > > I assume that Project is somehow extrapolating from task timelines
>> > > > (which I
>> > > > also sometimes assign, i.e. I manually put in start and finish
>> > > > dates) and/or
>> > > > resource availability, but how to I stop it from doing this?
>> > > > Thanks,
>> > > > Jeff- Hide quoted text -
>> >
>> > - Show quoted text -
>>
>