Farmgirl
Thu Aug 18 10:42:21 CDT 2005
John,
Unfortunately I have not worked with Project for years and I have forgotten
a lot. Thank you for your time in responding to my question. I will look
into the link that you sent also.
"John" wrote:
> In article <CB8068BA-D492-4E8F-B755-7C0E753866F9@microsoft.com>,
> "Farmgirl" <Farmgirl@discussions.microsoft.com> wrote:
>
> > I am using Project 2000 and am struggling trying to allocate more than 1
> > resource for a task. Am I allowed to do this, and if so how?
>
> Formgirl,
> Yes, you can assign as many resources as needed to any given task.
> Assuming you have already entered the resources onto the Resource Sheet,
> probably the easiest way is to select the task and then hit the Assign
> Resources icon (two heads) on the standard toolbar. In the Assign
> Resources window that pops up you will see all of the resources listed.
> Simply enter either a decimal or percent in the Units column and hit
> "Assign" each time.
>
> It sounds like you are relatively new to Project. May I suggest you take
> a look at a series of Project topics by one of my fellow MVPs, Mike
> Glen. Go to the MVP website at:
>
http://www.mvps.org/project/links.htm
> and click on the link to Mike's series of lessons and techniques.
>
> Hope this helps.
> John
> Project MVP
>