Re: How do I move an entire group of tasks by John
John
Fri Aug 29 15:41:22 CDT 2008
In article <447EFA81-1A1E-4B1E-8D47-D17DBFDE819B@microsoft.com>,
Dana Scott <DanaScott@discussions.microsoft.com> wrote:
> John
>
> I was also wondering if a pattern of links could be copied.
>
> As we move through the hospital floor by floor, the pattern of work is
> repeated. Is there a way to duplicate the timing of the links, but with new
> tasks? (Something similar to copy and paste in Excel where it understands you
> want to change referenced cell values when you paste the formula in an
> adjacent cell)
>
> Thank you
Dana,
It looks like you posted this in a separate new post and fellow MVP,
Jan, answered it.
One caution about using a direct copy and paste. No two (or group) of
tasks in any given schedule are identical. If they were, they would be
the exact same task. For example, in your case, similar tasks are
repeated but each group is unique to a floor in the building. Therefore,
the task description (task Name field) should reflect that distinction.
It makes the plan much cleared and easier to track.
John
Project MVP
>
> "John" wrote:
>
> > In article <EA882BE4-15C9-4515-929C-D0D7EAAC3C32@microsoft.com>,
> > Dana Scott <Dana Scott@discussions.microsoft.com> wrote:
> >
> > > Hello
> > >
> > > I am using Project 2007 to help manage Hospital Construction for a
> > > contractor. What I am trying to do is move the start date of a group of
> > > tasks, either earlier or later, based on changing conditions. If one
> > > trade
> > > (i.e. plumbing) needs to adjust their schedule, the timing of the group
> > > of
> > > tasks needs to stay the same (or relatively so), but the tasks do not all
> > > occur immediately following one another, this allows time for other
> > > trades to
> > > perform their work.
> > >
> > > So if I have 13 tasks spread over 150 days with several 10-20 day time
> > > gaps
> > > and I need to move the start date earlier, I have to adjust each one
> > > individually. I have tried hard and soft constraints, but cannot get
> > > that
> > > time gap to remain fixed.
> > >
> > > With thousands of tasks and years on the schedule, this can get a little
> > > tedious. I have looked some macros that may help this, but haven't found
> > > anything to fit the bill.
> > >
> > > I welcome any advice, and thank you in advance for your help
> >
> > Dana,
> > If you wanted to move the whole schedule earlier or later, the Adjust
> > Dates utility would do exactly that, but it will not move a select group
> > of tasks.
> >
> > It sounds like your plan doesn't have much of a linked structure, that
> > is, tasks are more-or-less scheduled independently. A much better way to
> > set up the plan is to have a fully linked dynamic schedule. Use lag in
> > task predecessors where necessary to put known delay between tasks.
> > Avoid the use of constraints since they defeat the ability of Project to
> > automatically adjust the schedule as reality unfolds during plan
> > execution.
> >
> > Yes you could change you plan with a macro similar to what the Adjust
> > Dates utility does but instead, I suggest you revise your plan to link
> > the schedule. Then all you will need to do is to adjust the link to the
> > first of the 13 tasks that you need to move earlier or later. Not only
> > will it be easier to make adjustments but you will also have a dynamic
> > plan that better emulates the real world.
> >
> > Probably not the answer you wanted to hear, but taking the time now to
> > address a not-so-well conceived plan is much better than struggling with
> > a poorly structured plan throughout the whole period of execution.
> >
> > John
> > Project MVP
> >