Re: microsoft project 2000 custom critical path by BBoler
BBoler
Thu Jul 28 11:35:02 CDT 2005
I have taken this discussion to the Development Discussion Board becuase I
think my problem may require VBA. The problem is that I don't want the CP
calculated for EVERY endpoint in my schedule, only three specific ones.
"Jim Spiller" wrote:
> Go to Tools-Options-Calculations and select "Calculate Multiple Critical
> Paths". It will then calculate a critical path to each end point in your
> project.
>
>
> "BBoler" <BBoler@discussions.microsoft.com> wrote in message
> news:1249F8AC-B0B0-457D-8690-833698B114C2@microsoft.com...
> >I know that MS Project 2000 will either calculate one critical path or
> > calculate all of the critical paths. I want to create three differeent
> > critical paths based on three specific milestones all in one project
> > schedule. Is this possible?
> >
> >
>
>
>