Change print display dates for a gantt chart
I am using microsoft project 2003 and I used an old schedule for a template.
I adjusted all the gantt dates for the project and I can see it on the
screen, but when I do a print preview the gantt chart is still displaying the
timefield from the template I used and nothing is displayed in the chart area.
Help
Shelby k. Johnson Tag: why microsoft office product is not compatible with U3 software?? Tag: 121727
Task wont both start Saturday an finish following Sunday, Project
I cant seem to figure out how to make a 9 day task start on Saturday and then
finish on the following Sunday, does not seem to want to count the weekends
as working days. Calendar is setup for 24 hour day/ Tag: why microsoft office product is not compatible with U3 software?? Tag: 121723
scheduling software
if your looking for a light weight scheduling application for
appointment based business such as salons, tanning, medical, see
http://www.salonoperations.com or http://www.grantparksoftware.com Tag: why microsoft office product is not compatible with U3 software?? Tag: 121716
USAsoft selling converter illegally?
hi, I found USAsoft (http://www.dvd-ipod-tool.com), which sold
USA Video to DVD Converter
USA DVD Video Mp4 Converter
USA DVD to Mp4 Platinum
USA DVD Video Ipod Converter
USA DVD Video Sony PSP Converter
USA DVD Video Cell Phone Converter
that everything is same as Total Video Converter 2.52 by merely
changing the program name & the interface.
Total Video Converter 2.52 can be downloaded from
http://www.effectmatrix.com/total-video-converter/tvc252old.exe
you will find it is same if you have basic software technical
knowledge
So, what do you think of this kind of issue? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121714
why are the right hours not showing
i am just trying to recreate another's project and im not getting the same
numbers.
the hours worked is different and the finish date is different.
the hours worked is different even though im using the same resources
assigned.
the finish date is different even though im using the same calandar.
what is going on with these discrepancies? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121697
Planned % Complete in MS Project 2000
Is there a "planned % complete" based on a selected baseline of a Project.
My problem is that I have to compare the actual % complete with the planned
percentage. How can I do this in MS Project 2000? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121695
Dynamic tables in MS Project 2000
I am currently tracking a Project. I designed a personalized view with the
baseline and actual data to help me with the tracking.
However, the deadlines are very short and baselines change frequently. So I
need to change the baseline over and over (I'm working on the third
baseline). The problem is that every time I update the baseline, my
personalized view gets out of date and I have to redesign it again.
Is there a method in which I can define a dynamic column? I mean, set a
column as "the last baseline end-date" or something like that?
Thanks! Tag: why microsoft office product is not compatible with U3 software?? Tag: 121694
Display multiple baselines in MS Project 2000
Fellas,
How can I display multiple baselines in MS Project 2000? I cannot find that
view.
Thanks! Tag: why microsoft office product is not compatible with U3 software?? Tag: 121693
Almost there need a bit of help
I am currently working on a macros that will take the percent complete from
an excel sheet and copy it to my project file. Currently I have it to do a
VLOOKUP on column A in excel with the Task Name in Project. if those are okay
it will copy the percent over to project. That was easy enough to write. The
problem I am having is I need it to look at and compare 2 columns in excel
and validate them with Task name and Text6 column in Project before it will
copy the percent complete from the excel sheet to Project.
Thanks for any help anyone can give on this. I can supply the code I have
now if it would be helpful. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121677
How do I show a hidden column in Project 2000?
I hid a column and am trying to unhide it. I tried the following-- select the
column to the right of the hidden column; select Insert a column; named it
the same as the hidden column. But I got a column with random, meaningless
numbers instead of the hidden column.
Help!
chrisl Tag: why microsoft office product is not compatible with U3 software?? Tag: 121675
Converted Hours
What's the best way to track "Converted Hours" (actual labor hours w/ actual
labor rates compared to baseline hours with baseline labor cost) and "Average
Labor Rates" per day and/or task. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121670
Project 2000, after row 50 or so,cell contents don't appear
I have a user that has about 4 or 5 Microsoft Project files that have the
info in the Task Name column, not appear in all the rows after row 50 or so.
They all dissappear starting at different rows.
--
Rke5858 Tag: why microsoft office product is not compatible with U3 software?? Tag: 121667
Inactive Global - Project 2007
Just installed the 2007 Project EPM system. When I go to "Delete Enterprise
Objects>Delete projects only from Published database" from Project Web
Access it lists Enterprise Global as "Inactive Global" under the Type heading.
In addition, when I check-out enterprise global from Project Professional
and go to "Delete Enterprise Objects>Delete projects only from Published
database" it does not recognize enterprise global as being "checked-out".
Any thoughts? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121665
Project 2003 Sample
Does MS Project 2003 have a sample project built in to work with?
Something similar to the Northwind sample database in Access. Thanks Tag: why microsoft office product is not compatible with U3 software?? Tag: 121662
Understanding the import merge key
When importing/merging from Excel using a map, I've specified a Merge Key for
each table coming in; tasks, resources, and assignments. The basic concept of
this key makes sense so the correct record can be matched and updated.
However, I am trying to find out more about how Project uses this as I am
baffled by an error that I think relates to my lack of understanding this
mechanism.
I'm importing from a workbook with a tasks, resources, and assignments tab.
I've assigned a text field as the merge field for all three. This imports
without error for the Tasks and Resources, even with non-numeric text in the
field. However, for the Assignments table, if that field contains text and
not a number I get an error dialog with this message, "The number you
entered is invalid or it is outside the range for a Number field. Make sure
you are typing only numbers and no letters or other characters in this field,
or type a smaller number." Again, this only occurs for the Assignments table.
If I change the value in the Assignments merge key field to a number instead
of text, the error goes away. And it seems that the Assignments merge key is
relating to the Unique ID field in the task list, regardless of what I
specify as the merge key in the Tasks table. Is the Import mechanism
hard-wired to relate the assigments merge key to *only* the Unique ID field?
Aside from my specific problem (which I probably didn't explain clearly
enough), can someone either explain more about the merge key to me or point
me to some source for a deeper explanation than is in the basic MS Project
help?
Thanks!
- Dale Tag: why microsoft office product is not compatible with U3 software?? Tag: 121657
How do I change from AM/PM scale to military time in MS Project?
Right now all the start and finish times in my project are shown as AM/PM
(i.e. 3:02 PM), but I want it to show up as 1502 instead (considered
'military time'). Can this be done? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121653
=?Utf-8?Q?Want_to_add_mtl_resource_to_task?=
I have a resource loaded schedule. Tasks are fixed duration. I have
captured the labor hour estimates in the â??workâ?? field. With fixed duration
tasks, changes in the labor estimates or duration, dynamically changes the %
allocated of the resources assigned.
I have a (non human) resource associated with some tasks. This resource is
a â??Labâ?? needed for the execution of specific tasks. This resource, like all
assigned resources, has a limited capacity. Adding this resource to a task
increases the â??Workâ?? associated a fixed duration task. Because the resource
is not a human resource, I do not want â??Labâ?? to increase the â??Workâ?? when
added to a task.
Adding â??Labâ?? to appropriate tasks, with an availability of 100% (8 hr./day,
Mon â?? Fri), I can see, like other resources, when the resource is over
allocated. I know then that I have to consider working more than one shift
to maintain overall schedule. In actuality, using the Lab does not increase
the labor estimate for a taskâ?¦ but MSP does increase the â??Workâ?? when any
additional resources are added to a fixed duration task.
I canâ??t seem to get MSP to allow me to add a resource (with an availability
of 100% (8 hr./day, Mon â?? Fri)), without increasing the â??Workâ?? for that task.
Iâ??m essentially trying to do capacity planning for the lab.
Bottom line â?? I want to add a resource to a task, with an availability of
100% (8 hr./day, Mon â?? Fri), and have that particular not affect (increase)
the â??Workâ?? for that fixed duration task.
I hope this clarifies the issue. Any thoughts are appreciated. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121652
Can't mail merge now. Something to do with ODC
While trying to sort a scanned copy of someone signiture and put it into
email I have somehow turned something off in word. Not sure what it is I have
done. But something called odc or something like that uodated. Now I can't
mail merge. Can anyone help is this a matter of removing the update? Many
thanks Tag: why microsoft office product is not compatible with U3 software?? Tag: 121651
How to add a new column in MSP 2003 with a reference number...
...which relates to a number of different tasks but not all. Specifically I
am thinking of giving a sub-project a unique number, which will relate to a
series of tasks.
I'm quite new at this, and can't find any helpful info in my textbook in the
software help. I am baffled by the field types in the column definition
dialogue box.
Can anyone help? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121645
GLobal.mpt import
Hi,
I have installed MS PRoject 2003 on a second computer, I would like to
import all my settings(filter, toolbars etc) from the previous system to the
new system.
Is there a way to do this? In other words I would like to keep my settings
in the new installation.
Thanks
--
Saviz Tag: why microsoft office product is not compatible with U3 software?? Tag: 121643
send
the send in Microfsoft office button won't open up send. It is stuck on fax
How can I send? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121641
Best practice for software development scheduling
Hi Project Gurus,
I'm currently in the business of delivering software billing solution
for large corporate and government clients using a shared pool of
resources (matrix organisation). A typical project is broken down by
Project>Phase>Iteration>Milestone>Task. During the course of a
project, the schedule is regularly changed to meet the constraints
imposed by a common pool of resources. This results in a substantial
amount of time redeveloping large schedules time and time again. In
particular, the task dependencies and task duration are constantly
shifting.
My question is this: is there a best practice methodology to minimise
the administrative overhead when scheduling software dev projects.
Many thanks
Tom Tag: why microsoft office product is not compatible with U3 software?? Tag: 121639
100% COMPLETE but still receiving OVERDUE email alerts
I recently 100%-ed every task out on a perticular project and even
republished the assignments (and checked the box to over-write the time that
had been entered by my resources) and myself and other resources on the
project are STILL receiving OVERDUE email alerts...what did I do wrong?
Please help...thanks! Tag: why microsoft office product is not compatible with U3 software?? Tag: 121633
how do I get project gantt charts to open on the current date
Project files open on the project start date when viewing the gantt charts.
How do I get the file to open on the current date. This project spans many
months so it is a pain having to always scroll to the current date after
opening. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121622
valid inputs for duration field
How to get valid inputs for duration field? (3 d, 3 days, 3 m, 3
months???)
Thanks for any help. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121616
MS Project 2003. How do I get the first task line to be a zero?
In creating a new project, I want the first task line to be a zero number. I
have seen projects done that way but when I try to set one up, the first line
is always 1. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121615
Network Diagram Software for Server 2003 & 2007
I'm looking for software that does Network Diagrams in the Project Server
environment. Does anyone know if an application(s) exists? We currently use
Pert Chart Expert, but it does not work directly through the server. Thank
you. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121613
Reports
Does anyone know where the report generator gets the information that it
displays at the top of the report? And how to modify that?
thanks Tag: why microsoft office product is not compatible with U3 software?? Tag: 121612
when i add predecessor +12 days it doesnt move it 12 working days
when i add predecessor +12 days it doesnt move it 12 working days as defined
by my working hours, instead it counts with not working saturdays, even though
i defined it to work saturdays,
later, i got it to show the right day, but starting in the middle of the day Tag: why microsoft office product is not compatible with U3 software?? Tag: 121610
gantt chart view
how do u get the wording next to the graph to show hours, not resources Tag: why microsoft office product is not compatible with U3 software?? Tag: 121609
Error updating assignments imported from Excel
I'm importing tasks, resources and assignements from Excel, using a map and
following the great information from various other posts. I'm having a
problem when importing updated assignments.
I have a resource assigned to a task and it imports just fine the first
time. I change the Work value in the assignment record in Excel and then
import it again. When I do, I get an error dialog with this message, "You
cannot have the same resource assigned twice to the same task. To have the
same person work at different times on the same task use resource
contouring." I am importing Unique_ID, Task_ID (Text 1), Task_Name,
Resource_Name, and Work.
Thanks in advance for any help and please ask if you want more details.
- Dale Tag: why microsoft office product is not compatible with U3 software?? Tag: 121607
Can Project Server 2003 re-publish automatically projects ??
i want to know if can project server re-publish automatically all the
projects without project professional. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121604
Project 2007: Save as 2003 format, and password protect?
This may be a newbie quesiton, but here goes...
I have a project created in MS Project 2007. I'd like to save it in a 2003
file format, and password protect it at the same time. When I select
"Microsoft Project 2000-2003" as the "Save as type", then all of the password
fields are disabled when I select tools->general options on the "Save As"
dialogue box. The "Protection Password" box is enabled if I try to save it
as a Project 2007 file type. Does anyone know why this is?
Thanks! Tag: why microsoft office product is not compatible with U3 software?? Tag: 121603
Proj 2003. Adjusting task duration according to Resource Availabil
I am using Microsoft Office Project Professional 2003.
I have defined my project, added all the tasks with expected durations, and
organised all these tasks into phases. All the durations were calculated at
the planning stage based on a single resource working 100% of their time on
the task.
All the task are 'Fixed Unit' type and 'Effort Driven'.
I am now at the stage where I want to setup and assign the available
resources, and I have run into a couple of problems.
I am anticipating that a proportion of the resources assigned to the project
will be working at about 80% productivity. It seemed that the easiest way to
represent this information in Project was to open up the Resource Information
for the pertinent resources and change their 'Resource Availability' to 80%.
However, when I assign a resource with a lower than 100% availability to a
task, it does not adjust the duration accordingly. It seems to be making the
assumption that the duration was initially calculated with the lower
availability in mind. If you then change the resource to someone with a
different 'Resource Availability' it does change the duration. I had a read
through the help - and although I couldn't ascertain for certain, I believe
this is the intended behaviour?
I made the assumption this was the case, and tried an alternative approach.
I changed the Resource Availability back to 100% via the Resource Information
dialogue. On the Gantt Chart I then assigned this resource to the relevant
tasks. I then went back to the Resource Information and changed the Resources
Availability down to 80%. The task duration did not change - I had to
re-assign the same resource manually to get it to update correctly.
I couldn't find anyway of getting the task duration to update automatically
when changing the availability of a resource. I even tried levelling - and
this just reported it as an error.
I would be surprised if this was the expected behaviour? Can you recommend
an alternative approach, or an option I may be missing?
Many thanks, Tag: why microsoft office product is not compatible with U3 software?? Tag: 121602
value list base calculation
I defined an Enterprise Number Field from type Number on a Task level that
indicates to which department the task belongs: 1,2,3 or 4. The numbers are
defined in the Value List.
I'm trying to create an Enterprise Project Number filed from type Number
that will show again on a task level, if the Enterprise Number Field = 1 than
the Enterprise Project Number = 1 too. if the Enterprise Number Field = 2
than the Enterprise Project Number = 2 and so on. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121599
Locking a task after hiding subtasks?
Is there a way to lock a task after hiding itâ??s subtask, so when you change
Outline View Levels you donâ??t have to re-hide everything? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121597
Trial Period Expired Project Server 2007
I have a problem. In my organization have three server configuration farm.
In first server install a SharePoint Server 2007 in second install Project
Server 2007, third is database server SQl Server 2005 with all database.
Farm correctly work last 3 weeks. On monday when users try to connect
Project Server system display 'Trial Period Expired'. All software have
enterprise license key.
I try to connect SharePoint Server 2007 and Central administration site, all
worked correctly and have access to project workspace with URL-address.
Need idea why this happend on relize ProjectServer 2007?
In event viewer see this errors
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description
Microsoft.Office.Server.Search.Administration.SearchAdminSharedWebServiceInstance (fcf1f604-5528-44e8-9c89-34c1edadae31).
Requested registry access is not allowed.
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description:
Microsoft.Office.Excel.Server.ExcelServerSharedWebServiceInstance
(283aa3b4-f0b5-4201-b173-83bde3db4fac).
Requested registry access is not allowed.
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Excel.Server.ExcelServerSharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description
Microsoft.Office.Project.Server.Administration.ProjectApplicationServiceInstance (913447e8-acc3-49cb-ac79-6dc872ca27a4).
Requested registry access is not allowed.
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Ð?бÑ?ие Ñ?лÑ?жбÑ? Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description:
Сбой заданиÑ? админиÑ?Ñ?Ñ?иÑ?ованиÑ? Ñ?еÑ?веÑ?а пÑ?иложений длÑ? Ñ?кземплÑ?Ñ?а Ñ?лÑ?жбÑ?
Microsoft.Office.Server.Search.Administration.SearchAdminSharedWebServiceInstance (fcf1f604-5528-44e8-9c89-34c1edadae31).
Ð?Ñ?иÑ?ина: Requested registry access is not allowed.
СведениÑ? о Ñ?еÑ?ниÑ?еÑ?кой поддеÑ?жке:
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Ð?бÑ?ие Ñ?лÑ?жбÑ? Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description:
Сбой заданиÑ? админиÑ?Ñ?Ñ?иÑ?ованиÑ? Ñ?еÑ?веÑ?а пÑ?иложений длÑ? Ñ?кземплÑ?Ñ?а Ñ?лÑ?жбÑ?
Microsoft.Office.Excel.Server.ExcelServerSharedWebServiceInstance
(283aa3b4-f0b5-4201-b173-83bde3db4fac).
Ð?Ñ?иÑ?ина: Requested registry access is not allowed.
СведениÑ? о Ñ?еÑ?ниÑ?еÑ?кой поддеÑ?жке:
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Excel.Server.ExcelServerSharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer
Event Type: Error
Event Source: Office SharePoint Server
Event Category: Ð?бÑ?ие Ñ?лÑ?жбÑ? Office Server
Event ID: 6482
Date: 14.05.2007
Time: 10:07:15
User: N/A
Computer: PROJECT1
Description:
Сбой заданиÑ? админиÑ?Ñ?Ñ?иÑ?ованиÑ? Ñ?еÑ?веÑ?а пÑ?иложений длÑ? Ñ?кземплÑ?Ñ?а Ñ?лÑ?жбÑ?
Microsoft.Office.Project.Server.Administration.ProjectApplicationServiceInstance (913447e8-acc3-49cb-ac79-6dc872ca27a4).
Ð?Ñ?иÑ?ина: Requested registry access is not allowed.
СведениÑ? о Ñ?еÑ?ниÑ?еÑ?кой поддеÑ?жке:
System.Security.SecurityException: Requested registry access is not allowed.
at System.ThrowHelper.ThrowSecurityException(ExceptionResource resource)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name, Boolean writable)
at Microsoft.Win32.RegistryKey.OpenSubKey(String name)
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.GetInstallPath()
at
Microsoft.Office.Server.Administration.SharedWebServiceInstance.Synchronize()
at
Microsoft.Office.Server.Administration.ApplicationServerJob.ProvisionLocalSharedServiceInstances(Boolean isAdministrationServiceJob)
The Zone of the assembly that failed was:
MyComputer Tag: why microsoft office product is not compatible with U3 software?? Tag: 121593
Problem with alignment of project web page
Hi,
I have an .mpp file I am trying to save as web.
I click save as web, use existing map and the "Who does what", and the
web page is created.
The issue is that the "resource and assignment" column is aligned to
the right instead of to the left.
The result is, instead of such a structure:
task1
task23
etc.
instead of:
task1
task23
etc.
I couldn't find how to change this.
Does anyone have a clue on how to resolve?
Thanks,
Amir. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121592
PWA activity not auto populating
We recently implemented a project 07 server including project web access
(PWA). I am trying to create an activity or proposal in PWA. I enter all of
the required information in summary information and then begin entering
information on the work details screen. When I enter a new task, it should
populate with the line number 1,2,3, etc. and I cannot enter the number
manually. If I try to save the work details without the number assignment, I
receive the following error, "Failed to enable constraints. One or more rows
contain values violating non-null, unique, or foreign-key constraints."
Any assistance would be greatly appreciated. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121583
Project
Dear All
Trying to use project in diary style for a weekly event, where arrival times
and finishing times are key. How do i set this up in project to reflect this?
Cheers
Mark Tag: why microsoft office product is not compatible with U3 software?? Tag: 121578
MS Project Developer
Hi,
We are looking for a MS Project Developer in Edmonton, AB - Canada
Please contact me at cholotron@hotmail.com
Regards, Tag: why microsoft office product is not compatible with U3 software?? Tag: 121577
bar style setups
I might be double posting here coz I'm not sure my reply to a post by
starting a new thread would get any response but here goes.
Is it possible to "import" the bar styles format of a file into other files
much like what the organizer could do? I have tried using templates but is
there another way?
TIA
D Pingger Tag: why microsoft office product is not compatible with U3 software?? Tag: 121576
resource allocation
how do i find out how many tasks a resource has been assigned to in MS Projet
2003 Tag: why microsoft office product is not compatible with U3 software?? Tag: 121566
Recieve Task Updates Via Standard Email
Is there a way to set up Project to send out emails asking for a task
completion percent, and then have the returned, updated completions updated
into the schedule? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121556
Task Start/End based on Predecessors
Does anyone know how I can configure a task so that its start date is based
on the start date of one task and its end date is based on the end of another
task?
I have tried to put both predecessor tasks in with the start one having a
start/start dependency and the end task with finish/finish - no luck. I am
really looking for MSP to calculate the duration and have the auto
adjustments be made if I have to adjust the predecessor tasks. Tag: why microsoft office product is not compatible with U3 software?? Tag: 121555
maximum lines in project???
I have a user that has a project that is around 900 to 1000 lines. sometimes
when she opens it some of the lines are missing under the task name section
of the project, sometimes they are not. the next time she opens it she may
be missing lines under something else and the ones that were missing before
are there.
The project is password protected and only two users have access to it.
I know with Excel there is a certain amount of lines you can have before it
starts acting goofy.
Is project the same? Does anyone know how many lines you can have before
you start having issues?
I had heard from someone that if you get a project around 1k lines, it will
start to have problems, but I do not know for sure.
She is using Project 2k3 pro.
--
Thanks
Dan Tag: why microsoft office product is not compatible with U3 software?? Tag: 121554
forcing resource list to get published.
We have been adding resources. They show up in MSP_WEB_RESOURCES
and not in
MSP_VIEW_RES_STD
MSP_VIEW_RES_ENT
I cannot see the new resources in Resource Center view on PWA
It looks like the resource list has not been published?
How can I force a resource list publish? Tag: why microsoft office product is not compatible with U3 software?? Tag: 121550