Re: How to make task duration of 3 calendar months, in MS Project by EitanF
EitanF
Tue Mar 08 11:03:03 CST 2005
Thanks, your complementary answer was very helpful.
"John" wrote:
> In article <1429000A-83F3-4F84-A085-6DFAECB1FC1F@microsoft.com>,
> JulieS <JulieS@discussions.microsoft.com> wrote:
>
> > Hi Eitan-F,
> >
> > The duration measurement "month" is defined on the Tools>Options, calendar
> > tab. By default it is defined as 20 working days. It is not variable. I
> > suggest using days or if you want to count nonworking time in the duration,
> > edays.
> >
> > Hope this helps. Let us know how you get along.
> >
> > Julie
> >
> > "Eitan-F" wrote:
> >
> > > I would like to count 3 calader months (28/31/30 days) for a task.
> > > What is the syntex in the 'Duration' column?
> > > The syntax: 3 mons, and 3 emons, both does not do it.
>
> Eitan-F,
> One clarification to what Julie stated. The setting for "month" in
> Tools/Options is a single setting for all months. In that regard it is
> not "variable" from month to month. But it is changeable by the user.
> You could adjust it to be "30" which is slightly more than the average
> (i.e. 29.666) of the three months you noted in your post. However I
> doubt that is what you really want. Of all the possibilities for entries
> in the Duration field, "month" is the least accurate. I suggest you use
> days or weeks instead.
>
> Hope this helps.
> John
> Project MVP
>