Re: how do I lock a task id number in ms project? by JulieS
JulieS
Thu Apr 20 12:06:10 CDT 2006
Hi Erin,
Try using the Unique ID field. It functions as you need.
I hope this helps. Let us know how you get along.
Julie
"erin" <erin@discussions.microsoft.com> wrote in message
news:C9F9DE31-D312-4C7B-A20E-07747CE4AE8C@microsoft.com...
>I would like to lock the task id's in my schedule so that they do not
> renumber themselves every time a task is added. Is there a way to do
> this?