davegb
Fri Jul 09 12:45:53 CDT 2004
Maybe you have a resource unavailable until after the start date of the project.
David G. Bellamy
Bellamy Consulting
"Mike Glen" <glenATmvps.org> wrote in message news:<OYm4kFEZEHA.2016@TK2MSFTNGP09.phx.gbl>...
> Hi Daniele,
>
> Welcome to this Microsoft Project newsgroup :-)
>
> Check any calendars you have in Tools/Change Working Hours. Make sure you
> have no summaries with the resource assigned. Try levelling to a different
> granularity like hour by hour. I can't think of anything else - post back.
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: <
http://www.mvps.org/project/>
>
> Hope this helps - please let us know how you get on :-))
>
> Mike Glen
> MS Project MVP
>
>
> "daniariete2000" <daniariete2000@yahoo.it> wrote in message
> news:6aebcd65.0407070549.7f2f7920@posting.google.com...
> > Hello !
> > My problem is :
> > I have 5 consolidated projects with just a resource allocated to them.
> > There are several overallocations and when I try to use levelling
> > there is a gap at the beginning of first task in first project. In
> > other words..the start date of first project is transslated without
> > any reasons.
> > Anyone can help me ?
> >
> > Thanks
> >
> > Daniele