RE: last updated or date complete by pratta
pratta
Tue Apr 19 19:50:02 CDT 2005
Hi GF
I think what you are after is being able to set the date the task finished.
Try Tools/Tracking/Update Task.
If you set the finish date Project will assume the task is complete, which
is a reasonable assumption.
Otherwise, check Current Date in Project/Project Information and with the
task selected use the Update Task as scheduled OR Reschedule Task icons as
applicable.
When maintaining schedules like this I like to insert a "current date" line
on the Gantt. Do this by right clicking in the Gantt and then select
Gridlines/Current Date and select the color. Any incomplete tasks in the
gantt on the left of the line need to be either:
- marked as completed
- re-echeduled
- partly completed and re-scheduled
- or deleted
Regards..........Pratta
"godfearer" wrote:
> I would like to know when a task has been set to 100% complete. I don't want
> to know the finish date, because that seems to be the date it was projected
> to be finished and the actual date doesn't seem to be the moment when it was
> set to 100% complete either. Anybody got a field for me to use?