Mike
Wed May 07 09:02:01 CDT 2008
Hi Tommy,
Welcome to this Microsoft Project newsgroup :)
From the Gantt Chart view, click where you want the task to go. Then select
Insert/New Task or click the Insert button on your keyboard. Does that
work? You could also try right-clicking the ID number of the task below
where you want it to go and select New Task.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
"Tommy-Project 2007 Novice" <Tommy-Project 2007
Novice@discussions.microsoft.com> wrote in message
news:A42455F0-5CAB-4607-B9CD-306105E41B0B@microsoft.com...
>I am trying to insert a new task into the middle of an existing chart, but
> the option to insert a new task is grayed out. It will let me add one to
> the
> bottom of the chart works, but how can Insert lines in the middle?