When initially setting-up a project does it matter if you
add work or duration before reasources?

Re: initial set-up of plan by Gérard

Gérard
Mon Jan 26 15:00:46 CST 2004

Hello Paul,

Yes, you can define a task by it's Duration and it's load of Work
Then set the Task Type to Fixed Duration.
When you'll assign a resource to that task, Ms Project will calculate the
Units:
Duration x Units = Work

Gérard Ducouret



"Paul" <anonymous@discussions.microsoft.com> a écrit dans le message de
news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> When initially setting-up a project does it matter if you
> add work or duration before reasources?



Re: initial set-up of plan by Jan

Jan
Mon Jan 26 23:22:40 CST 2004

Hi all,

BTW, this is true for ll task types, not just for Fixd Duration.

- You always better enter duration
You CAN then enter work
If you do, when assigning a resource, units are calculated
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
"Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in bericht
news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> Hello Paul,
>
> Yes, you can define a task by it's Duration and it's load of Work
> Then set the Task Type to Fixed Duration.
> When you'll assign a resource to that task, Ms Project will calculate the
> Units:
> Duration x Units = Work
>
> Gérard Ducouret
>
>
>
> "Paul" <anonymous@discussions.microsoft.com> a écrit dans le message de
> news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > When initially setting-up a project does it matter if you
> > add work or duration before reasources?
>
>



Re: initial set-up of plan by Gérard

Gérard
Tue Jan 27 03:42:58 CST 2004

Hi Paul, hi Jan,

The task type doesn't matter when you enter the Work in the Assign Resources
dialog box. But if you enter it in the Work column inserted in any Table,
the Fixed Units for example yields a strange result :

Try the following : (I'm working with MSP 2002)

Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
Project Calculate : Units = 2, OK.

Task B : Duration 10d, Work : 20d (in the column) => Ms Project Calculate :
Units = 2 *AND* the Duration jumps to 20 d !

If you observe the Task Usage, there are 2 Units nowhere.



Haven't you observed this phenomenon ?



Gérard Ducouret

"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans le
message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> Hi all,
>
> BTW, this is true for ll task types, not just for Fixd Duration.
>
> - You always better enter duration
> You CAN then enter work
> If you do, when assigning a resource, units are calculated
> HTH
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> Project Management Consultancy
> Prom+ade BVBA
> 32-495-300 620
> "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in bericht
> news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > Hello Paul,
> >
> > Yes, you can define a task by it's Duration and it's load of Work
> > Then set the Task Type to Fixed Duration.
> > When you'll assign a resource to that task, Ms Project will calculate
the
> > Units:
> > Duration x Units = Work
> >
> > Gérard Ducouret
> >
> >
> >
> > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le message de
> > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > When initially setting-up a project does it matter if you
> > > add work or duration before reasources?
> >
> >
>
>



Re: initial set-up of plan by Jan

Jan
Tue Jan 27 05:55:30 CST 2004

Hi Gérard,

I mostly use 2000, and there it works like a charm
In 2002, it's even more weird than that.
When the resulting units are less than 100% it works perfectly, units are
calculated allright, but when the resulting units WOULD be >100% the
behaviour is as you describe.

Why won't they leave things that work well alone when making a new release?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
"Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in bericht
news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> Hi Paul, hi Jan,
>
> The task type doesn't matter when you enter the Work in the Assign
Resources
> dialog box. But if you enter it in the Work column inserted in any Table,
> the Fixed Units for example yields a strange result :
>
> Try the following : (I'm working with MSP 2002)
>
> Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> Project Calculate : Units = 2, OK.
>
> Task B : Duration 10d, Work : 20d (in the column) => Ms Project Calculate
:
> Units = 2 *AND* the Duration jumps to 20 d !
>
> If you observe the Task Usage, there are 2 Units nowhere.
>
>
>
> Haven't you observed this phenomenon ?
>
>
>
> Gérard Ducouret
>
> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans le
> message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > Hi all,
> >
> > BTW, this is true for ll task types, not just for Fixd Duration.
> >
> > - You always better enter duration
> > You CAN then enter work
> > If you do, when assigning a resource, units are calculated
> > HTH
> >
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> > Project Management Consultancy
> > Prom+ade BVBA
> > 32-495-300 620
> > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in bericht
> > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > Hello Paul,
> > >
> > > Yes, you can define a task by it's Duration and it's load of Work
> > > Then set the Task Type to Fixed Duration.
> > > When you'll assign a resource to that task, Ms Project will calculate
> the
> > > Units:
> > > Duration x Units = Work
> > >
> > > Gérard Ducouret
> > >
> > >
> > >
> > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le message
de
> > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > When initially setting-up a project does it matter if you
> > > > add work or duration before reasources?
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by Steve

Steve
Tue Jan 27 06:08:19 CST 2004

Where are you seeing units without resources being assigned for your
Task B? How are you entering 20d for units in Task A?

When I do your experiment with Task B in Proj 2003, it appears the
calculation is "on hold" until the resources are assigned. After
defining 2 resources and entering the task with a duration of 10 days
and a work of 20, nothing happens. Then opening the resource list box,
selecting one resource and hitting "assign" results in a 100% assignment
and a duration of 20 days while selecting both resources and hitting
assign results in both assigned at 100% and the duration remains at 10
days. (Task Type is the default fixed units). Instead of recalculating
units, when assigning resources to a task that already has a work
estimate, Proj 203 assumes a 100% resource assignment for all resources
assigned together and fixed work, then recalculates duration accordingly
which seems to me to be a very reasonable approach. I don't understand
this love affair so many people seem to have with fixed duration tasks.

--
Steve House
MS Project MVP
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> Hi Paul, hi Jan,
>
> The task type doesn't matter when you enter the Work in the Assign
Resources
> dialog box. But if you enter it in the Work column inserted in any
Table,
> the Fixed Units for example yields a strange result :
>
> Try the following : (I'm working with MSP 2002)
>
> Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> Project Calculate : Units = 2, OK.
>
> Task B : Duration 10d, Work : 20d (in the column) => Ms Project
Calculate :
> Units = 2 *AND* the Duration jumps to 20 d !
>
> If you observe the Task Usage, there are 2 Units nowhere.
>
>
>
> Haven't you observed this phenomenon ?
>
>
>
> Gérard Ducouret
>
> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
le
> message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > Hi all,
> >
> > BTW, this is true for ll task types, not just for Fixd Duration.
> >
> > - You always better enter duration
> > You CAN then enter work
> > If you do, when assigning a resource, units are calculated
> > HTH
> >
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> > Project Management Consultancy
> > Prom+ade BVBA
> > 32-495-300 620
> > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
bericht
> > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > Hello Paul,
> > >
> > > Yes, you can define a task by it's Duration and it's load of Work
> > > Then set the Task Type to Fixed Duration.
> > > When you'll assign a resource to that task, Ms Project will
calculate
> the
> > > Units:
> > > Duration x Units = Work
> > >
> > > Gérard Ducouret
> > >
> > >
> > >
> > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
message de
> > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > When initially setting-up a project does it matter if you
> > > > add work or duration before reasources?
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by Gérard

Gérard
Tue Jan 27 06:57:13 CST 2004

Hello Steve,

>>How are you entering 20d for units in Task A?>> :
In the Assign Resources dialog box, in the "Units" cell in front of the
resource name that I expect to assign.

>>Proj 2003 assumes a 100% resource assignment for all resources assigned
together and fixed work, then recalculates duration accordingly<<
I would agree if Project 2002 would really do that. The issue is that MSP
2002 displays a 200% assignment while it manages a 100% assignment.
So we have something like that :
20d duration x 2 units = 20 days of work !!!
(NB: I tried this in the 2002 version, it worked differently in the previous
versions, and I did not tried it in 2003).

Gérard Ducouret

"Steve House" <sjhouse.remove.this@to.send.hotmail.com> a écrit dans le
message de news: 4016540e$0$3719$45beb828@newscene.com...
> Where are you seeing units without resources being assigned for your
> Task B? >
> When I do your experiment with Task B in Proj 2003, it appears the
> calculation is "on hold" until the resources are assigned. After
> defining 2 resources and entering the task with a duration of 10 days
> and a work of 20, nothing happens. Then opening the resource list box,
> selecting one resource and hitting "assign" results in a 100% assignment
> and a duration of 20 days while selecting both resources and hitting
> assign results in both assigned at 100% and the duration remains at 10
> days. (Task Type is the default fixed units). Instead of recalculating
> units, when assigning resources to a task that already has a work
> estimate, Proj 203 assumes a 100% resource assignment for all resources
> assigned together and fixed work, then recalculates duration accordingly
> which seems to me to be a very reasonable approach. I don't understand
> this love affair so many people seem to have with fixed duration tasks.
>
> --
> Steve House
> MS Project MVP
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
> news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> > Hi Paul, hi Jan,
> >
> > The task type doesn't matter when you enter the Work in the Assign
> Resources
> > dialog box. But if you enter it in the Work column inserted in any
> Table,
> > the Fixed Units for example yields a strange result :
> >
> > Try the following : (I'm working with MSP 2002)
> >
> > Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> > Project Calculate : Units = 2, OK.
> >
> > Task B : Duration 10d, Work : 20d (in the column) => Ms Project
> Calculate :
> > Units = 2 *AND* the Duration jumps to 20 d !
> >
> > If you observe the Task Usage, there are 2 Units nowhere.
> >
> >
> >
> > Haven't you observed this phenomenon ?
> >
> >
> >
> > Gérard Ducouret
> >
> > "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
> le
> > message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > > Hi all,
> > >
> > > BTW, this is true for ll task types, not just for Fixd Duration.
> > >
> > > - You always better enter duration
> > > You CAN then enter work
> > > If you do, when assigning a resource, units are calculated
> > > HTH
> > >
> > > --
> > > Jan De Messemaeker
> > > Microsoft Project Most Valuable Professional
> > > Project Management Consultancy
> > > Prom+ade BVBA
> > > 32-495-300 620
> > > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
> bericht
> > > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > > Hello Paul,
> > > >
> > > > Yes, you can define a task by it's Duration and it's load of Work
> > > > Then set the Task Type to Fixed Duration.
> > > > When you'll assign a resource to that task, Ms Project will
> calculate
> > the
> > > > Units:
> > > > Duration x Units = Work
> > > >
> > > > Gérard Ducouret
> > > >
> > > >
> > > >
> > > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
> message de
> > > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > > When initially setting-up a project does it matter if you
> > > > > add work or duration before reasources?
> > > >
> > > >
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by Gérard

Gérard
Tue Jan 27 07:24:42 CST 2004

PS :
<<I don't understand this love affair so many people seem to have with fixed
duration tasks<<
I don't have any love affair with fixed duration tasks ;-)
Less than 0.1% of my tasks are set to Fixed Duration in my projects.

Gérard Ducouret

"Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> a écrit dans le message
de news: uhTCuTN5DHA.1636@TK2MSFTNGP12.phx.gbl...
> Hello Steve,
>
> >>How are you entering 20d for units in Task A?>> :
> In the Assign Resources dialog box, in the "Units" cell in front of the
> resource name that I expect to assign.
>
> >>Proj 2003 assumes a 100% resource assignment for all resources assigned
> together and fixed work, then recalculates duration accordingly<<
> I would agree if Project 2002 would really do that. The issue is that MSP
> 2002 displays a 200% assignment while it manages a 100% assignment.
> So we have something like that :
> 20d duration x 2 units = 20 days of work !!!
> (NB: I tried this in the 2002 version, it worked differently in the
previous
> versions, and I did not tried it in 2003).
>
> Gérard Ducouret
>
> "Steve House" <sjhouse.remove.this@to.send.hotmail.com> a écrit dans le
> message de news: 4016540e$0$3719$45beb828@newscene.com...
> > Where are you seeing units without resources being assigned for your
> > Task B? >
> > When I do your experiment with Task B in Proj 2003, it appears the
> > calculation is "on hold" until the resources are assigned. After
> > defining 2 resources and entering the task with a duration of 10 days
> > and a work of 20, nothing happens. Then opening the resource list box,
> > selecting one resource and hitting "assign" results in a 100% assignment
> > and a duration of 20 days while selecting both resources and hitting
> > assign results in both assigned at 100% and the duration remains at 10
> > days. (Task Type is the default fixed units). Instead of recalculating
> > units, when assigning resources to a task that already has a work
> > estimate, Proj 203 assumes a 100% resource assignment for all resources
> > assigned together and fixed work, then recalculates duration accordingly
> > which seems to me to be a very reasonable approach. I don't understand
> > this love affair so many people seem to have with fixed duration tasks.
> >
> > --
> > Steve House
> > MS Project MVP
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
> > news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> > > Hi Paul, hi Jan,
> > >
> > > The task type doesn't matter when you enter the Work in the Assign
> > Resources
> > > dialog box. But if you enter it in the Work column inserted in any
> > Table,
> > > the Fixed Units for example yields a strange result :
> > >
> > > Try the following : (I'm working with MSP 2002)
> > >
> > > Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> > > Project Calculate : Units = 2, OK.
> > >
> > > Task B : Duration 10d, Work : 20d (in the column) => Ms Project
> > Calculate :
> > > Units = 2 *AND* the Duration jumps to 20 d !
> > >
> > > If you observe the Task Usage, there are 2 Units nowhere.
> > >
> > >
> > >
> > > Haven't you observed this phenomenon ?
> > >
> > >
> > >
> > > Gérard Ducouret
> > >
> > > "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
> > le
> > > message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > > > Hi all,
> > > >
> > > > BTW, this is true for ll task types, not just for Fixd Duration.
> > > >
> > > > - You always better enter duration
> > > > You CAN then enter work
> > > > If you do, when assigning a resource, units are calculated
> > > > HTH
> > > >
> > > > --
> > > > Jan De Messemaeker
> > > > Microsoft Project Most Valuable Professional
> > > > Project Management Consultancy
> > > > Prom+ade BVBA
> > > > 32-495-300 620
> > > > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
> > bericht
> > > > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > > > Hello Paul,
> > > > >
> > > > > Yes, you can define a task by it's Duration and it's load of Work
> > > > > Then set the Task Type to Fixed Duration.
> > > > > When you'll assign a resource to that task, Ms Project will
> > calculate
> > > the
> > > > > Units:
> > > > > Duration x Units = Work
> > > > >
> > > > > Gérard Ducouret
> > > > >
> > > > >
> > > > >
> > > > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
> > message de
> > > > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > > > When initially setting-up a project does it matter if you
> > > > > > add work or duration before reasources?
> > > > >
> > > > >
> > > >
> > > >
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by Gary

Gary
Tue Jan 27 07:40:57 CST 2004

Steve:

You need to think outside the classic PM box to understand this. It's not a
love affair, it's a necessity to model certain business processes that do
not fit into an "as soon as possible" scenario. It's evident that you have a
distinct bias toward effort-based planning, and I accept all of your
arguments for it as valid, however that ideal-state is often not desirable
or achievable. Thankfully, Project supports both methodologies.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
We wrote the book on Project Server


"Steve House" <sjhouse.remove.this@to.send.hotmail.com> wrote in message
news:4016540e$0$3719$45beb828@newscene.com...
> Where are you seeing units without resources being assigned for your
> Task B? How are you entering 20d for units in Task A?
>
> When I do your experiment with Task B in Proj 2003, it appears the
> calculation is "on hold" until the resources are assigned. After
> defining 2 resources and entering the task with a duration of 10 days
> and a work of 20, nothing happens. Then opening the resource list box,
> selecting one resource and hitting "assign" results in a 100% assignment
> and a duration of 20 days while selecting both resources and hitting
> assign results in both assigned at 100% and the duration remains at 10
> days. (Task Type is the default fixed units). Instead of recalculating
> units, when assigning resources to a task that already has a work
> estimate, Proj 203 assumes a 100% resource assignment for all resources
> assigned together and fixed work, then recalculates duration accordingly
> which seems to me to be a very reasonable approach. I don't understand
> this love affair so many people seem to have with fixed duration tasks.
>
> --
> Steve House
> MS Project MVP
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
> news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> > Hi Paul, hi Jan,
> >
> > The task type doesn't matter when you enter the Work in the Assign
> Resources
> > dialog box. But if you enter it in the Work column inserted in any
> Table,
> > the Fixed Units for example yields a strange result :
> >
> > Try the following : (I'm working with MSP 2002)
> >
> > Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> > Project Calculate : Units = 2, OK.
> >
> > Task B : Duration 10d, Work : 20d (in the column) => Ms Project
> Calculate :
> > Units = 2 *AND* the Duration jumps to 20 d !
> >
> > If you observe the Task Usage, there are 2 Units nowhere.
> >
> >
> >
> > Haven't you observed this phenomenon ?
> >
> >
> >
> > Gérard Ducouret
> >
> > "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
> le
> > message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > > Hi all,
> > >
> > > BTW, this is true for ll task types, not just for Fixd Duration.
> > >
> > > - You always better enter duration
> > > You CAN then enter work
> > > If you do, when assigning a resource, units are calculated
> > > HTH
> > >
> > > --
> > > Jan De Messemaeker
> > > Microsoft Project Most Valuable Professional
> > > Project Management Consultancy
> > > Prom+ade BVBA
> > > 32-495-300 620
> > > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
> bericht
> > > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > > Hello Paul,
> > > >
> > > > Yes, you can define a task by it's Duration and it's load of Work
> > > > Then set the Task Type to Fixed Duration.
> > > > When you'll assign a resource to that task, Ms Project will
> calculate
> > the
> > > > Units:
> > > > Duration x Units = Work
> > > >
> > > > Gérard Ducouret
> > > >
> > > >
> > > >
> > > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
> message de
> > > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > > When initially setting-up a project does it matter if you
> > > > > add work or duration before reasources?
> > > >
> > > >
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by student

student
Tue Jan 27 09:46:47 CST 2004

I agree completely Gary - I'm a big believer in the right tool for the job.
What I teach my classes is that the task type should be looked at for each
individual task immediately prior to changing any of the three WED values
with an eye to the question "Why am I changing this and what should happen
to the task when I do?" I view it as a control for the PM to use to direct
Project's scheduling engine's behavior toward the most accurate model and
not an attribute of the task per se. What I do see in a lot of my students
is that they have a preconceived notion of what the schedule *should* be and
then set tasks to fixed duration in an effort to prevent Project from
telling them different, even when it really should be doing so.

Steve House
MS PRoject MVP


"Gary L. Chefetz [MVP]" <garyNOSPAM@chefetzDOTorg> wrote in message
news:eMVr3KO5DHA.360@TK2MSFTNGP12.phx.gbl...
> Steve:
>
> You need to think outside the classic PM box to understand this. It's not
a
> love affair, it's a necessity to model certain business processes that do
> not fit into an "as soon as possible" scenario. It's evident that you have
a
> distinct bias toward effort-based planning, and I accept all of your
> arguments for it as valid, however that ideal-state is often not desirable
> or achievable. Thankfully, Project supports both methodologies.
>
> --
>
> Gary Chefetz [MVP]
> http://www.msprojectexperts.com
> We wrote the book on Project Server
>
>
> "Steve House" <sjhouse.remove.this@to.send.hotmail.com> wrote in message
> news:4016540e$0$3719$45beb828@newscene.com...
> > Where are you seeing units without resources being assigned for your
> > Task B? How are you entering 20d for units in Task A?
> >
> > When I do your experiment with Task B in Proj 2003, it appears the
> > calculation is "on hold" until the resources are assigned. After
> > defining 2 resources and entering the task with a duration of 10 days
> > and a work of 20, nothing happens. Then opening the resource list box,
> > selecting one resource and hitting "assign" results in a 100% assignment
> > and a duration of 20 days while selecting both resources and hitting
> > assign results in both assigned at 100% and the duration remains at 10
> > days. (Task Type is the default fixed units). Instead of recalculating
> > units, when assigning resources to a task that already has a work
> > estimate, Proj 203 assumes a 100% resource assignment for all resources
> > assigned together and fixed work, then recalculates duration accordingly
> > which seems to me to be a very reasonable approach. I don't understand
> > this love affair so many people seem to have with fixed duration tasks.
> >
> > --
> > Steve House
> > MS Project MVP
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
> > news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> > > Hi Paul, hi Jan,
> > >
> > > The task type doesn't matter when you enter the Work in the Assign
> > Resources
> > > dialog box. But if you enter it in the Work column inserted in any
> > Table,
> > > the Fixed Units for example yields a strange result :
> > >
> > > Try the following : (I'm working with MSP 2002)
> > >
> > > Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> > > Project Calculate : Units = 2, OK.
> > >
> > > Task B : Duration 10d, Work : 20d (in the column) => Ms Project
> > Calculate :
> > > Units = 2 *AND* the Duration jumps to 20 d !
> > >
> > > If you observe the Task Usage, there are 2 Units nowhere.
> > >
> > >
> > >
> > > Haven't you observed this phenomenon ?
> > >
> > >
> > >
> > > Gérard Ducouret
> > >
> > > "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
> > le
> > > message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > > > Hi all,
> > > >
> > > > BTW, this is true for ll task types, not just for Fixd Duration.
> > > >
> > > > - You always better enter duration
> > > > You CAN then enter work
> > > > If you do, when assigning a resource, units are calculated
> > > > HTH
> > > >
> > > > --
> > > > Jan De Messemaeker
> > > > Microsoft Project Most Valuable Professional
> > > > Project Management Consultancy
> > > > Prom+ade BVBA
> > > > 32-495-300 620
> > > > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
> > bericht
> > > > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > > > Hello Paul,
> > > > >
> > > > > Yes, you can define a task by it's Duration and it's load of Work
> > > > > Then set the Task Type to Fixed Duration.
> > > > > When you'll assign a resource to that task, Ms Project will
> > calculate
> > > the
> > > > > Units:
> > > > > Duration x Units = Work
> > > > >
> > > > > Gérard Ducouret
> > > > >
> > > > >
> > > > >
> > > > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
> > message de
> > > > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > > > When initially setting-up a project does it matter if you
> > > > > > add work or duration before reasources?
> > > > >
> > > > >
> > > >
> > > >
> > >
> > >
> >
> >
>
>



Re: initial set-up of plan by Steve

Steve
Tue Jan 27 10:22:05 CST 2004

Opps - wrong account
I agree completely Gary - I'm a big believer in the right tool for the job.
What I teach my classes is that the task type should be looked at for each
individual task immediately prior to changing any of the three WED values
with an eye to the question "Why am I changing this and what should happen
to the task when I do?" I view it as a control for the PM to use to direct
Project's scheduling engine's behavior toward the most accurate model and
not an attribute of the task per se. What I do see in a lot of my students
is that they have a preconceived notion of what the schedule *should* be and
then set tasks to fixed duration in an effort to prevent Project from
telling them different, even when it really should be doing so.

Steve House
MS PRoject MVP

"Gary L. Chefetz [MVP]" <garyNOSPAM@chefetzDOTorg> wrote in message
news:eMVr3KO5DHA.360@TK2MSFTNGP12.phx.gbl...
> Steve:
>
> You need to think outside the classic PM box to understand this. It's not
a
> love affair, it's a necessity to model certain business processes that do
> not fit into an "as soon as possible" scenario. It's evident that you have
a
> distinct bias toward effort-based planning, and I accept all of your
> arguments for it as valid, however that ideal-state is often not desirable
> or achievable. Thankfully, Project supports both methodologies.
>
> --
>
> Gary Chefetz [MVP]
> http://www.msprojectexperts.com
> We wrote the book on Project Server
>
>
> "Steve House" <sjhouse.remove.this@to.send.hotmail.com> wrote in message
> news:4016540e$0$3719$45beb828@newscene.com...
> > Where are you seeing units without resources being assigned for your
> > Task B? How are you entering 20d for units in Task A?
> >
> > When I do your experiment with Task B in Proj 2003, it appears the
> > calculation is "on hold" until the resources are assigned. After
> > defining 2 resources and entering the task with a duration of 10 days
> > and a work of 20, nothing happens. Then opening the resource list box,
> > selecting one resource and hitting "assign" results in a 100% assignment
> > and a duration of 20 days while selecting both resources and hitting
> > assign results in both assigned at 100% and the duration remains at 10
> > days. (Task Type is the default fixed units). Instead of recalculating
> > units, when assigning resources to a task that already has a work
> > estimate, Proj 203 assumes a 100% resource assignment for all resources
> > assigned together and fixed work, then recalculates duration accordingly
> > which seems to me to be a very reasonable approach. I don't understand
> > this love affair so many people seem to have with fixed duration tasks.
> >
> > --
> > Steve House
> > MS Project MVP
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> wrote in message
> > news:uF9ZLnL5DHA.1816@TK2MSFTNGP12.phx.gbl...
> > > Hi Paul, hi Jan,
> > >
> > > The task type doesn't matter when you enter the Work in the Assign
> > Resources
> > > dialog box. But if you enter it in the Work column inserted in any
> > Table,
> > > the Fixed Units for example yields a strange result :
> > >
> > > Try the following : (I'm working with MSP 2002)
> > >
> > > Task A : Duration 10d, Assign resource : 20d (in the Units cell) => Ms
> > > Project Calculate : Units = 2, OK.
> > >
> > > Task B : Duration 10d, Work : 20d (in the column) => Ms Project
> > Calculate :
> > > Units = 2 *AND* the Duration jumps to 20 d !
> > >
> > > If you observe the Task Usage, there are 2 Units nowhere.
> > >
> > >
> > >
> > > Haven't you observed this phenomenon ?
> > >
> > >
> > >
> > > Gérard Ducouret
> > >
> > > "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> a écrit dans
> > le
> > > message de news: etj3zZJ5DHA.2760@TK2MSFTNGP09.phx.gbl...
> > > > Hi all,
> > > >
> > > > BTW, this is true for ll task types, not just for Fixd Duration.
> > > >
> > > > - You always better enter duration
> > > > You CAN then enter work
> > > > If you do, when assigning a resource, units are calculated
> > > > HTH
> > > >
> > > > --
> > > > Jan De Messemaeker
> > > > Microsoft Project Most Valuable Professional
> > > > Project Management Consultancy
> > > > Prom+ade BVBA
> > > > 32-495-300 620
> > > > "Gérard Ducouret" <gerard.ducouret@wanadooNOSPAM.fr> schreef in
> > bericht
> > > > news:uAV0R9E5DHA.2008@TK2MSFTNGP10.phx.gbl...
> > > > > Hello Paul,
> > > > >
> > > > > Yes, you can define a task by it's Duration and it's load of Work
> > > > > Then set the Task Type to Fixed Duration.
> > > > > When you'll assign a resource to that task, Ms Project will
> > calculate
> > > the
> > > > > Units:
> > > > > Duration x Units = Work
> > > > >
> > > > > Gérard Ducouret
> > > > >
> > > > >
> > > > >
> > > > > "Paul" <anonymous@discussions.microsoft.com> a écrit dans le
> > message de
> > > > > news: 482701c3e446$625ea7c0$a001280a@phx.gbl...
> > > > > > When initially setting-up a project does it matter if you
> > > > > > add work or duration before reasources?
> > > > >
> > > > >
> > > >
> > > >
> > >
> > >
> >
> >
>
>