I have a large project and approximately 25 people sending me weekly
spreadsheets to update their actual hours worked. Not knowing the havoc that
it was going to create, I was importing those spreadsheets into my project
plan and updating the actual work column. Everything was working fine until
I just discovered that the actuals were updating future date. For example,
the plan allocates each resource to work 6.4 hours per day. That's a total
of 32 hours per week. If a resource sends in that they worked on a task for
40 hours that week and I increase the actual work column by 40, behind the
scenes project only puts 32 hours on the current week and then schedules the
rest for the following week.
One, I need to figure out how to get all the hours posted from the past 16
weeks to be backdated so there is no longer future dated actuals. And then,
two, I need to figure out how to post the actual hours by date instead of
just updating the actual work column....or is there a way to tell project to
force any overage to the current billing week.
Any help or insight would be appreciated.
--
Carol Summa