Dale
Wed Sep 03 10:43:17 CDT 2008
Microsoft Communities --
I assume you are using Project Server 2003. If so, in the future please
post your Project Server questions in the microsoft.public.project.server
newsgroup, as this newsgroup is dedicated to the Microsoft Project desktop
application only. To answer your question, refer to the following FAQ which
gives you a process for archiving completed projects so that the projects
and tasks in them are hidden:
http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/ArchiveCompletedProjects.aspx
You will need to tweak the methodology presented in the FAQ to hide
cancelled projects as well. Hope this helps.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"Microsoft Communities" <tuyen-db@fujinet.net> wrote in message
news:ejvCcIZDJHA.4800@TK2MSFTNGP06.phx.gbl...
> Dear Everyone,
>
> I have some finished and cancelled projects, and I want hide all task and
> project on Task and Project tab
>
> How to do in MSP 2003?
>
> Best regards
>
>