Mike
Fri Feb 17 14:28:04 CST 2006
Hi Andy,
Welcome to this Microsoft Project newsgroup :)
When you enter Actual Work, you need also to enter the Remaining Work,
whence Project will meet your requirements.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
Andy wrote:
> I am trying to update actual work perfomed in the "Resource Usage
> Sheet". The start and/or end dates are changing. How can I fix this?
> I have all the tasks marked as "fixed Duration" and have set
> caluction options to manual, yet the dates still change
>
> ?????