Re: how does Project calculate summary progress by John
John
Sat Jun 04 16:02:20 CDT 2005
In article <24E1D9E3-8E13-4661-8C11-E69B58881E94@microsoft.com>,
Tomcat <Tomcat@discussions.microsoft.com> wrote:
> Also if anyone has any further comments on the "Work schedule progress
> question" post below it would be greatly appreciated
Tomcat,
This question has been answered multiple times in the past. The short of
it is as follows:
Summary Line percent complete = (sum of subtask Actual Durations) / (sum
of subtask Durations) x 100%.
Note that subtasks are actual performance tasks. Using duration values
of other Summary lines does not work in the equation.
Hope this helps.
John