Is it possible to have REAL resources in MSProject 2003 SP3 synced to actual
and the GENERIC resources NOT sync to actual after having set %-complete on
tasks with Generic-ONLY sources.

In other words ... we'd like to track technical progress on tasks that only
have GENERIC resources assigned ... thus, if we set a %-complete, it will
estimate the remaining work on that task for that generic resource.

If I do this now, it resets that task back to 0% as the GENERICS don't
report time via PWA.

Re: differential sync to actual by Mike

Mike
Wed Dec 12 01:53:32 PST 2007

Hi ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



"Project Planner - University"
<ProjectPlannerUniversity@discussions.microsoft.com> wrote in message
news:EB9050BD-E1F5-4DBD-AFCF-225BD8CD7414@microsoft.com...
> Is it possible to have REAL resources in MSProject 2003 SP3 synced to
> actual
> and the GENERIC resources NOT sync to actual after having set %-complete
> on
> tasks with Generic-ONLY sources.
>
> In other words ... we'd like to track technical progress on tasks that
> only
> have GENERIC resources assigned ... thus, if we set a %-complete, it will
> estimate the remaining work on that task for that generic resource.
>
> If I do this now, it resets that task back to 0% as the GENERICS don't
> report time via PWA.