Tue Oct 09 00:58:51 PDT 2007
If people do less work during the first week of the project than the plan
had called for doesn't that mean it isn't proceeding as fast as planned and
will take longer to complete? If they do more than the plan had called for,
doesn't that mean they're getting it done quicker and the project will
finish sooner than first planned? You're asking to cripple Project's very
reason for existence.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs