Hi Guys,

I've a feeling that there could be a really obvious answer to this that
will have me slapping myself for my own stupidity, but I just can't
find it...

I've just completed an MS Project (MSP 2002) plan for the next 6 months
or so, but noticed that when I set the day length at the beginning, I
only managed to change Mondays to a non default time, and not the
entire week. The default time was 08:00 -> 17:00, but we have more
leisurely 09:00 -> 17:00 days around here.

The upshot is is that I've got all my durations and resources based on
a 9->5 day on Monday, then 8->5 every other day. How can I change all
the days to be 9->5? I've tried fiddling through the Tools->Change
Working Time menu, but can't work out how to change anything other than
a single day at a time...

Any help would be greatfully received!


Thanks in advance,

Chris

Re: change working time - adjust all days duration by Jan

Jan
Wed Jul 26 08:02:32 CDT 2006

Hi,

Tools, Change Working tiome
(So far so good)
Select the T for Tuesday, the W for Wennedsday, the T for Thusrday, the F
for Friday.
Do NOT select any particular date.
Now change the working times.

But don't be surprised your plan looks differently!
If you don't understand read FAQ 5 (URL in my signature)

A bit late, but you'll appreciate that in the courses I give my very first
advice is : set working time and clendars right BEFORE ENTERING even the
first task.

HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
<chris_culley@yahoo.com> schreef in bericht
news:1153918100.571787.194140@i3g2000cwc.googlegroups.com...
> Hi Guys,
>
> I've a feeling that there could be a really obvious answer to this that
> will have me slapping myself for my own stupidity, but I just can't
> find it...
>
> I've just completed an MS Project (MSP 2002) plan for the next 6 months
> or so, but noticed that when I set the day length at the beginning, I
> only managed to change Mondays to a non default time, and not the
> entire week. The default time was 08:00 -> 17:00, but we have more
> leisurely 09:00 -> 17:00 days around here.
>
> The upshot is is that I've got all my durations and resources based on
> a 9->5 day on Monday, then 8->5 every other day. How can I change all
> the days to be 9->5? I've tried fiddling through the Tools->Change
> Working Time menu, but can't work out how to change anything other than
> a single day at a time...
>
> Any help would be greatfully received!
>
>
> Thanks in advance,
>
> Chris
>



Re: change working time - adjust all days duration by chris_culley

chris_culley
Wed Jul 26 08:28:40 CDT 2006

there it is - <slap/>

Many thanks Jan



Jan De Messemaeker wrote:
> Hi,
>
> Tools, Change Working tiome
> (So far so good)
> Select the T for Tuesday, the W for Wennedsday, the T for Thusrday, the F
> for Friday.
> Do NOT select any particular date.
> Now change the working times.
>
> But don't be surprised your plan looks differently!
> If you don't understand read FAQ 5 (URL in my signature)
>
> A bit late, but you'll appreciate that in the courses I give my very first
> advice is : set working time and clendars right BEFORE ENTERING even the
> first task.
>
> HTH
>
> --
> Jan De Messemaeker, Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/
> For FAQs: http://www.mvps.org/project/faqs.htm
> <chris_culley@yahoo.com> schreef in bericht
> news:1153918100.571787.194140@i3g2000cwc.googlegroups.com...
> > Hi Guys,
> >
> > I've a feeling that there could be a really obvious answer to this that
> > will have me slapping myself for my own stupidity, but I just can't
> > find it...
> >
> > I've just completed an MS Project (MSP 2002) plan for the next 6 months
> > or so, but noticed that when I set the day length at the beginning, I
> > only managed to change Mondays to a non default time, and not the
> > entire week. The default time was 08:00 -> 17:00, but we have more
> > leisurely 09:00 -> 17:00 days around here.
> >
> > The upshot is is that I've got all my durations and resources based on
> > a 9->5 day on Monday, then 8->5 every other day. How can I change all
> > the days to be 9->5? I've tried fiddling through the Tools->Change
> > Working Time menu, but can't work out how to change anything other than
> > a single day at a time...
> >
> > Any help would be greatfully received!
> >
> >
> > Thanks in advance,
> >
> > Chris
> >