JulieS
Fri Nov 09 13:16:25 PST 2007
You're welcome and thanks for the feedback.
Julie
"s conklin" <sconklin@discussions.microsoft.com> wrote in message
news:4D055F07-5AE6-49CE-8BFD-37167868E3DB@microsoft.com...
> Julie, the F3 trick worked, I will try the other solutions for the
> other
> question you answered in a bit, thanks again
> 1
>
> "JulieS" wrote:
>
>> Hello S Conklin,
>>
>> There could be a couple of things going on:
>>
>> Tasks have been temporarily hidden by the application of a filter.
>> To
>> remove any possible filters, press the F3 key on your keyboard.
>>
>> You have sorted the project and tasks 13 - 20 are mixed in with other
>> tasks. To re-establish the normal ID order, choose Project Sort >
>> Sort
>> By > ID.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit
http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "s conklin" <sconklin@discussions.microsoft.com> wrote in message
>> news:725A846A-036D-4309-8D64-1A4CE7F2F9F6@microsoft.com...
>> >I am running Project 2003 standard and I have a break in the task
>> >sequencing
>> > it jumps from Task 12 to Task 21. Need to re-establish sequencing
>> > 13,
>> > 14,
>> > 15.21.
>> > i am not sure how this happens, can I get it back to sequential
>> > order?
>> > Thanks-
>>
>>
>>