RE: How do I set up assigned and unassigned work on Gantt Chart? by sai
sai
Wed Mar 12 22:36:00 CDT 2008
Hi -
I understand you are looking at options to assign task to a group of
resources.
I am new to shared work group, but a simple option is to create a work
resource representing a group, say Designer Group. If your Designer Group has
5 members, then have the [availability] units in Resource Information form
has 500%.
Drawbacks: Resource calendar is for the resource [Designer Group] and not
for the individual designers.
Please let us know if this helps.
Regards
Sai [PMP]
"CD103" wrote:
> I am looking for a quick fix on two things.
>
> 1). Group work assignments by shared groups (I've read the instructions,
> didn't help). Any simple way to do this will be appreciated.
>
> 2). Once I create the shared work groups, how do I show it on the Gantt
> Chart view.
>
> Thank you,
>
> CD103