Using project 4.0. I made a list of tasks for a project on January 21st for
a project that started last November for documentation.
How can I change the project start date back to November 1st without
having to respond to the 'task started before project' prompt for everything
I change?

Thanks

Re: alter project start date by Josh

Josh
Tue Jan 27 15:38:17 CST 2004

OK, I found it:
Tools - Macros - Adjust Dates

"Josh Whitney" <barrowcl@flash.net> wrote in message
news:eTb69wR5DHA.2440@TK2MSFTNGP09.phx.gbl...
> Using project 4.0. I made a list of tasks for a project on January 21st
for
> a project that started last November for documentation.
> How can I change the project start date back to November 1st without
> having to respond to the 'task started before project' prompt for
everything
> I change?
>
> Thanks
>
>