css34
Thu Jan 27 15:39:08 CST 2005
currently I am using the option called:
"Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task"
Thanks
"Dale Howard [MVP]" wrote:
> css34 --
>
> I believe that the Adjust Actuals feature assumes you are using the Hours of
> work done per day or per week method of tracking progress. Is that the
> method you are using to track progress in your organization? Let us know.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
>
http://www.msprojectexperts.com
> "We wrote the book on Project Server"
>
>
> "css34" <css34@discussions.microsoft.com> wrote in message
> news:BA3D301A-5635-410B-A36E-D8BCDAB40C8D@microsoft.com...
> >I am a PM with every permission in the book. When I go to the Resources
> >page
> > and select the adjust actuals link in the left hand pane, it brings me to
> > the
> > correct page, but all the boxes are read only. How do I update my
> > resources
> > taks for them through PWA?
>
>
>