I am a PM with every permission in the book. When I go to the Resources page
and select the adjust actuals link in the left hand pane, it brings me to the
correct page, but all the boxes are read only. How do I update my resources
taks for them through PWA?

Re: adjust actuals by Dale

Dale
Thu Jan 27 15:12:25 CST 2005

css34 --

I believe that the Adjust Actuals feature assumes you are using the Hours of
work done per day or per week method of tracking progress. Is that the
method you are using to track progress in your organization? Let us know.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"css34" <css34@discussions.microsoft.com> wrote in message
news:BA3D301A-5635-410B-A36E-D8BCDAB40C8D@microsoft.com...
>I am a PM with every permission in the book. When I go to the Resources
>page
> and select the adjust actuals link in the left hand pane, it brings me to
> the
> correct page, but all the boxes are read only. How do I update my
> resources
> taks for them through PWA?



Re: adjust actuals by css34

css34
Thu Jan 27 15:39:08 CST 2005

currently I am using the option called:

"Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task"

Thanks

"Dale Howard [MVP]" wrote:

> css34 --
>
> I believe that the Adjust Actuals feature assumes you are using the Hours of
> work done per day or per week method of tracking progress. Is that the
> method you are using to track progress in your organization? Let us know.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> "We wrote the book on Project Server"
>
>
> "css34" <css34@discussions.microsoft.com> wrote in message
> news:BA3D301A-5635-410B-A36E-D8BCDAB40C8D@microsoft.com...
> >I am a PM with every permission in the book. When I go to the Resources
> >page
> > and select the adjust actuals link in the left hand pane, it brings me to
> > the
> > correct page, but all the boxes are read only. How do I update my
> > resources
> > taks for them through PWA?
>
>
>