Mike
Thu Apr 19 08:04:45 CDT 2007
Hi George,
Welcome to this Microsoft Project newsgroup :)
The Duration field is the total span of active working time for a task. This
is generally the amount of working time from the start to the finish of a
task. Work is the time a resource spends towards the achievement of the
task, usually measured in man-hours. If a resource is assigned at 100%
using default calendars, then the Duration will be the same as the Work.
But it is not necessarily the same if, for example, you assign a resource at
50%, then the Work will be 40 man-hours for the 80-hour Duration as he is
only working half the time of the Duration, or only 4 hours per day.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
"George Furnell" <GeorgeFurnell@discussions.microsoft.com> wrote in message
news:E95F37D2-FA74-4C10-9197-0D9353487902@microsoft.com...
> Good day, and thanks for taking the time to read.
>
> I am planning a new project and since I am paying by the hour, I need to
> know how many hours it will take to do the work. I.e my budget will be
> hours
> * rate.
>
> Unfortunately I am confused and do not know the difference between the
> duration and the work column.
>
> Can you please explain?
>
> Kind regards
> George