Re: Visual Earned Value Over Time Report by Anna
Anna
Thu May 08 15:45:01 CDT 2008
I have the Earned Value Method set at % Complete. I only have one baseline.
and that was the one I chose by going to tools menu/options/calculation tab
and click the "Earned Value" button.
As far as fixed cost with actual, no I have not updated. I thought that was
calculated automatically through Project. When I go to view/tables/ more
tables/ earned value, the information is already calculated with the
exception of the CV (Cost Varience) field.
When I go to the visual earned value over time report the planned, earned,
and actual fields are 0 values.
Is there a table like the task or resource sheet or a view Task/resource)
that I should be in before clicking on reports to get those values to show
the correct values on the visual report?
"Jack Dahlgren" wrote:
> Anna,
>
> There are a number of ways to enter progress so that % complete is updated.
> You get to choose how you want to do that. The earned value calculation
> method can be configured to use either % Complete or Physical % Complete and
> also which baseline to compare against. You can set that by going to tools
> menu/options/calculation tab and click the "Earned Value" button.
>
> Have you updated your fixed costs with the actual costs to date?
>
> Planned cost should come from the baseline
> Actual cost should come from the actual cost
> Earned value is based on % complete (either regular or physical) x planned
> cost.
>
> -Jack Dahlgren
>
>
> "Anna" <Anna@discussions.microsoft.com> wrote in message
> news:B98670AD-1156-433A-B419-1AA8090382AE@microsoft.com...
> > Hi Jack!
> >
> > Resource have been assigned to the tasks. Cost have been entered in the
> > task
> > sheet under Fixed Cost because The costs are lump sum and not hourly.
> >
> > Should I enter the cost in the Resource sheet under fixed cost next to the
> > resource it's assigned to?
> >
> > The baseline and staus dates have been assigned as well.
> >
> > What do you mean by actual work done? % Complet? Physical % Complete? or 5
> > Work Complete? or actual against remaining duration?
> >
> > "Jack Dahlgren" wrote:
> >
> >> First, you need to assign resources to tasks within your project with
> >> costs
> >> associated with them.
> >> Second you need to set a baseline. Have you done that?
> >> Third, you need to set the status date. Have you done that?
> >> Finally you need to update the tasks with actual work done.
> >>
> >> Then the reports would be valid.
> >>
> >> -Jack Dahlgren
> >>
> >> "Anna" <Anna@discussions.microsoft.com> wrote in message
> >> news:101DC4CE-4A43-446D-BC19-F41C17C6C83A@microsoft.com...
> >> > I'm working in MS Project 2007 and the service pack is installed.
> >> >
> >> > When I try to generate an earned value over time report by going to
> >> > reports/visual reports/excel/earned value over time report/view, then
> >> > clicking on Assignment Usage with EV tab, I am receiving 0 values.
> >> >
> >> > If I double click the Q2 it will drop down the weeks. If I double click
> >> > the
> >> > items listed under type in the Pivot table field list, the
> >> > only value showing is under costs.
> >> >
> >> > How do you get the values to read under the planned, earned and actuals
> >> > columns?
> >> >
> >> >
> >> >
> >> >
> >>
> >>
> >>
>
>
>