I'm trying to generate a particular view of my project plan. Here's the
scenario:
I have a project with the following structure...
Task
Subtask
Activity

When I sort or group the information in the plan, I want the Subtask and
Task name to be visible on the same line as the Activity. For example, I'd
like to be able to populate one of the Text fields with "Task, Subtask".
This would enable me to maintain a reference to the WBS while looking at an
Activity in isolation.

Is there a way to do this?

Re: View Summary Task in-line with Subtasks by Jan

Jan
Wed Mar 19 01:30:14 CDT 2008

Hi,

Only through a VBA procedure I'm afraid.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"projectnovice" <projectnovice@discussions.microsoft.com> wrote in message
news:4105ADC5-9FF9-4465-96FB-0B5C7E04D2D1@microsoft.com...
> I'm trying to generate a particular view of my project plan. Here's the
> scenario:
> I have a project with the following structure...
> Task
> Subtask
> Activity
>
> When I sort or group the information in the plan, I want the Subtask and
> Task name to be visible on the same line as the Activity. For example,
> I'd
> like to be able to populate one of the Text fields with "Task, Subtask".
> This would enable me to maintain a reference to the WBS while looking at
> an
> Activity in isolation.
>
> Is there a way to do this?