smokingbull
Tue Jul 25 13:20:02 CDT 2006
Thanks Jan !
I think that's the only way to order the views.
"Jan De Messemaeker" wrote:
> Hi,
>
> Their order is first, task driven views, then resource driven views, sorted
> alppha in both groups.
> Sio when you change the name in Tools, Organizer, Views, rename, you will
> have a different oirder.
> For instace the a_Tracking Gantt would appear first.
> Hope this helps.
>
> --
> Jan De Messemaeker
> Microsoft Project MVP
> +32 495 300 620
>
http://users.online.be/prom-ade
> "smokingbull" <smokingbull@discussions.microsoft.com> wrote in message
> news:895CD8D9-611B-4C0C-99DA-4615EC8BFD0F@microsoft.com...
> >
> > Hello everyone,
> >
> > Is there a way to change the order of views in the viewbar ? Not a big
> > issue, but It'd be nice to arrange..
> >
> > Thanks
>
>
>