Re: Updating the schedule with progress by wolseley6
wolseley6
Thu Mar 10 02:24:18 CST 2005
"=?Utf-8?B?SGFpeGlhbmc=?=" <haixiang.zhang@mw-zander.com> wrote in message news:<AAFEA4B4-E29E-4771-BA5A-18D1C3F1C952@microsoft.com>...
> To update progress for large project is really difficult.
> hope my story helps.
> the management group for the project prepared the master schedule.
> the master schedule contain more than 6000 tasks.
> Subs were responsible to make their detail construction schedule based on
> the master schedule. for example there was a task (Task A start on day1 and
> finish on day100),subcontractor will make a schedule with tasks
> A1,A2,A3.....An( A1 start on day1 and An finish on day100, so they are the
> children of task A). we established a numbering system with it we can easily
> identify the tasks in master schedule to their "children" in subs schedule,
> then we can summarize progress info. of these "children" to the tasks in
> master schedule.
> All subs detail tasks add up to about 100000,and we update on a weekly basis.
> Every week all subs are required to submit their updated detail schedules to
> us.
> Thanks to the numbering system, we can update our master schedule
> automatically by using the data from the subs.
> After update, we perform a analysis (critical path report), and then have a
> meeting with all subs to tell them what they need to do,what they need to
> take care.
>
> In fact the subs can only give us the summarised tasks,we seldom review
> those 100000 tasks, we just summarise them and update our master schedule.
>
> So if your subs do not like to give you detail, tell them to give you a
> summary which can meet your needs. (ensure the summary match your master
> tasks or it will be difficult to update your schedule based on those
> summarys)
>
> At that time we use Privamera, it has the ability to make all subs'
> schedules into a single project group, just as we insert subproject in a
> master project in MSP. let subs to update their schedule and we can see the
> result in the master schedule. But we did not do this, it will take hours to
> just open the project. And it is impossible for the project management group
> to set up the links between those 100000 tasks from dozens of different
> contractors
>
>
> "Andy" wrote:
>
> > "Sarah" <sarahkiko@hotmail.com> wrote in message news:<1110375549.756085.218120@z14g2000cwz.googlegroups.com>...
> > > The only thing I would add is that, when you get a new finish date from
> > > a sub, don't just enter the date in the Finish field. Modify the
> > > Duration field until the Finish field shows the date you were given.
> > > This will avoid putting a constraint on the task, but will move out
> > > successor tasks.
> >
> >
> > Yes, agree entirely. I have avoided as many constraints as possible
> > anyway and don't wish to start introducing them.
> >
> > The only problem I have now is that the subs as such are feeling
> > exposed by this as it obviously gives more visibility of their
> > activity. Ideally we should be using an EPM tool (Project Server
> > perhaps).
> > This is a large programme I am working on and to be honest is very
> > badly set up for scheduling. So, I have tried to set up the process as
> > mentioned in order to lessen the burdon on what info the subs have to
> > provide to me on a weekly basis.
> >
> > Any views on this?
> >
> > Andy
> >
Thanks for this; really helpfull actually.
Our subcontractors are insisting at the moment that they cannot
possibly update their schedules weekly. They have such a detailed
process that it takes a month to get through. However, I have yet to
see a usefull update once a month to be honest!
So, this causes us a huge problem; by the time we have an update from
them it is useless as it is already out of date and any risks we
should be mitigating have already occurred and turned into issues!
In order to try and reach a compromise we have set up a top-level
schedule with tasks from all parties summarised (aligned with xref to
uniqueID's) and linked together. We only expect them to report on
tasks that are currently in progress or should have started on a
weekly basis and then a review of the entire schedule once a month.
This was an attempt to try and reduce the burdon on them but is
obviously not ideal. This is still a problem for them!
I have now suggested that even an update based on a perception from
their Project Managers on the summary tasks weekly would do, but they
still argue that this cannot be done!
We have some phases of the programme that are expected to be complete
in 6 months time and just having 6 updates I think is inadequate.
Does anybody disagree/agree with my approach?
Thanks again,
Andy.
p.s. This was my first time at this newsgroup yesterday; fantastic to
have these responses. Think it might prevent me going mad; we are
having some major problems at the moment!!!