Mike
Thu Dec 13 04:22:05 PST 2007
Hi SonT,
Welcome to this Microsoft Project newsgroup :)
You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #27 on data input, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
"SonT" <SonT@discussions.microsoft.com> wrote in message
news:EB68F980-9617-4152-97F5-A23BAAA12C75@microsoft.com...
> Please advise what is the best way to update task progress in schedule.
>
> 1) % Complete
> 2) Actual Duration/Remaining Duration
> 3) Actual Work/Remaining Work
>
> Thanks in advance.