Wed Oct 27 05:29:56 CDT 2004
Hi Sarah,
Welcome to this Microsoft Project newsgroup :-)
On the Analysis tool bar, click the Adjust Dates macro button.
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on :-))
Mike Glen
MS Project MVP
Sarah A wrote:
> Is it possible to move forward all tasks within a project by several
> weeks, rather than going into each task and moving the start and
> finish dates individually?