Re: Total Resource Cost by WalterIsley
WalterIsley
Tue Jan 10 14:50:02 CST 2006
Thanks JulieS,
This looks good. I'll give it a shot.
"JulieS" wrote:
> Hi Walter,
>
> Project does not perform an average function for total cost. I think what
> may be tripping you up is the amount of *work* that each resource is
> scheduled to do on the task. By setting the task to fixed duration but
> leaving the task as an effort driven task, project keeping the original
> amount of work stable and drops the assignment units for each resource
> added. Because project calculates costs by work * rate, it appears as
> though project is averaging the cost.
> To illustrate:
> Split your screen from the Gantt chart (Window > Split) to show the task
> form at the bottom.
> Create a 1 day duration task, and in the task form selected fixed Duration,
> and keep the check in effort driven. Click OK. When you assign the first
> resource at 100%, 8 hours of work is calculated on the one-day duration
> task. When you add a second resource, the duration remains at 1 day and
> because the task is effort driven, the total amount of work remains the
> same -- 8 hours -- and each resource's assignment units drops to 50%. The
> tasks still costs the same because the amount of work (8 hours) is the same.
>
> Create another 1 day duration task, fixed Duration but non-effort driven.
> For each resource assigned, project just calculates an additional 8 hours of
> work. The cost of the task increases as you add additional resources.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> "Walter Isley" <WalterIsley@discussions.microsoft.com> wrote in message
> news:BAC7071E-D994-4BDF-A61E-08627D77EACC@microsoft.com...
> > First let me set the stage.
> >
> > I have created my resource sheet to include an hourly standard rate per
> > resource.
> >
> >
> > On tasks that require multiple resources, I want the system to add the
> > total
> > sum verses coming with an average. Example four resources @ $50 per hour
> > should show a total cost of $200.00 for a one hour activity verses the
> > average of $50.
> >
> >
> > (I've set my template to "fixed duration")
> >
> >
> >
> > How can I get the system to show total sum verses average?
> >
> >
>
>
>