JulieS
Fri Apr 18 16:02:12 CDT 2008
Hello Chama,
As you have discovered, tasks (Gantt chart view) and Resources each
have a set of custom fields and a data entered into one side, does not
display in the other field.
See FAQs 37 & 51 at
http://project.mvps.org/faqs.htm for some
additional information. FAQ # 37 also has two sample macros to copy
data from one field to another.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"Chama" <Chama@discussions.microsoft.com> wrote in message
news:FB5DD344-249E-40F6-80E7-C23647A55410@microsoft.com...
> The text fields I have inserted and renamed in the Gantt Chart view
> don't
> carry over to the Resource View.
>
> I want to put different charge numbers against each task and I want
> to see
> that charge number when I change to the Resource View.
>
> Any ideas?