Hi,

When I have a few tasks all linked. If I change the start time or
duration of one of the tasks all the tasks before it will change and
the ones below wont.

What I am trying to do is move the task in the middle and then have all
the ones below move forward and not the ones before.

I hope it is clear, if not please ask.

Thanks for your help in advance.

Re: Tasks keep moving by AlanStotty

AlanStotty
Tue Sep 12 04:20:50 CDT 2006

Worked it out. Need to have project information to start time.


AlanStotty wrote:
> Hi,
>
> When I have a few tasks all linked. If I change the start time or
> duration of one of the tasks all the tasks before it will change and
> the ones below wont.
>
> What I am trying to do is move the task in the middle and then have all
> the ones below move forward and not the ones before.
>
> I hope it is clear, if not please ask.
>
> Thanks for your help in advance.