Mike
Fri Oct 07 08:48:53 CDT 2005
Hi Omega30,
Welcome to this Microsoft Project newsgroup :-)
Please bear in mind Project is not an accounting program but a scheduling
program. It is thus unlikely to be of sufficient accuracy to satisfy
accountants! That said, you might like to see FAQ Item: 5. Default Working
Hours
FAQs, companion products and other useful Project information can be seen at
this web address:
http://www.mvps.org/project/
Hope this helps - please let us know how you get on :-)
Mike Glen
Project MVP
Omega430 wrote:
> I scheduled several projects, assigned resources and have a standard
> 8 hour day set up with 1/2 hour for lunch. 7a - 3:30p. When I
> switched the view to task usage, it showed all my resources listed as
> working 7 hours a day. I want this to reflect 8 hours in a work day.
> Which setting do I cahange to make this default? This is more for a
> billing thing, so I need to know man hours we are charging for.
>
> Thanks