JulieS
Tue Mar 11 12:55:05 CDT 2008
Hello UK,
It sounds as though there is a mismatch between your project calendar
and the definition of the number of hours per day.
Please see FAQ 5 "Default Working Hours" at
http://project.mvps.org/faqs.htm
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"UK" <UK@discussions.microsoft.com> wrote in message
news:BB2C570F-CDCA-4692-93DE-03266949FF95@microsoft.com...
>I have a one day task that starts at 8:00 am and ends at 5:00 pm, yet
>the
> number in the duration column field shows as .86. When I change the
> duration
> column field to 1 day, it makes the end time 9:09 am the next day. If
> I try
> to load 8 hours for a resource in this task (the task is a fixed work
> type
> task), it says that the resource is over allocated. Can you tell me
> what
> might be causing this?