I am currently working a large plan for multiple sites. The Base calendar is
the normal 8 to 5 M-F with weekends off. I have one task the long pole which
is 120 days lead time but the days are consectutive. The 120 day task has
constraints within the normal plan. I'm having trouble getting the 120 day
task to be 120 days because of the constraints to the normal calendar. How
do I fix this??

Thanks
--
Mike Milos

Re: Task calendar different than the Base calendar by Jonathan

Jonathan
Thu May 08 09:50:48 CDT 2008

Mike

Have you tried creating and then applying a "working weekend" type calendar
to the 120 day task? This is done under "Advanced Tab" of the task
information screen? If you have resources assigned to this task also check
the box to "ignore resource calendars".

Jonathan


"mmilos" <mmilos@discussions.microsoft.com> wrote in message
news:6D9D644B-8E8A-414C-A497-543EB4C857AE@microsoft.com...
>I am currently working a large plan for multiple sites. The Base calendar
>is
> the normal 8 to 5 M-F with weekends off. I have one task the long pole
> which
> is 120 days lead time but the days are consectutive. The 120 day task has
> constraints within the normal plan. I'm having trouble getting the 120
> day
> task to be 120 days because of the constraints to the normal calendar.
> How
> do I fix this??
>
> Thanks
> --
> Mike Milos



Re: Task calendar different than the Base calendar by Mike

Mike
Thu May 08 10:24:40 CDT 2008

Hi mmilos,

Welcome to this Microsoft Project newsgroup :)

Have you tried a lead of 120ed for elapsed days?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials


mmilos wrote:
> I am currently working a large plan for multiple sites. The Base
> calendar is the normal 8 to 5 M-F with weekends off. I have one task
> the long pole which is 120 days lead time but the days are
> consectutive. The 120 day task has constraints within the normal
> plan. I'm having trouble getting the 120 day task to be 120 days
> because of the constraints to the normal calendar. How do I fix
> this??
>
> Thanks